[Issue] Honam Expressway Expansion Project Breaks Ground After Delays...Challenges Remain
Full-Scale Construction Begins 12 Years After Passing Feasibility Review
Progress Rate at 2.02%…Completion Targeted for 2029
Cultural Heritage Survey and 400 Billion Won in Local Funding Remain Key Variables
The Honam Expressway Gwangju section expansion project, originally scheduled for completion in 2021, is still under construction as of July 2026.
When the expansion work for the Donggwangju IC to Gwangsan IC section, which passes through downtown Gwangju, passed its preliminary feasibility study in 2013, it aimed to start construction in 2017 and finish in 2021. However, construction did not begin until September last year. During that time, the total project budget nearly tripled from 276.2 billion won to 793.4 billion won.
The project, which had a challenging start, faced an additional variable this year due to a cultural heritage survey. Following the launch of Jeonnam Gwangju Integrated Special City, further discussions emerged to review the allocation of nearly 400 billion won in local government funding. While construction has commenced, there are still many hurdles to be cleared before the targeted completion in 2029.
As the project has faced prolonged delays, the frustration of residents in nearby areas, where traffic congestion is chronic, has deepened. There had been hope among residents that the persistent traffic jams would be resolved following last year's groundbreaking. However, new discussions around reassessing the provincial funding burden have renewed concerns that the project may once again be delayed.
Kim, a 45-year-old office worker who has lived in Yongbong-dong, Buk-gu for 20 years and uses the Honam Expressway for his daily commute, said, "Whenever it's time to go home, cars trying to enter the expressway line up, and even the local roads in the neighborhood become completely blocked. When I heard about the groundbreaking last year, I thought we would finally get some relief, but now with talk of another review, it just feels frustrating."
He also said, "Shouldn't the issues concerning the construction costs and funding have been settled before the groundbreaking? For the citizens who have endured more than a decade of traffic congestion, I hope the project is finally completed as planned."
Started as a Two-Lane Road: Honam Expressway Stretched to Its Limits by Urban Growth
The congestion on this road worsened because the pace of urban expansion outstripped the expressway’s capacity. The Gwangju stretch of the Honam Expressway first opened in 1973 as a two-lane road, then expanded to four lanes in 1986. While it originally served as a bypass around Gwangju, continued urban growth changed the situation. With the addition of Yongbong, Dongnim, Sanwol, and Munheung interchanges, the expressway took on the role of a main arterial road for daily commutes for Gwangju citizens, not just long-distance travel.
While the road itself remained the same, the number of vehicles continued to increase, causing routine congestion during peak commuting hours. In response, the city of Gwangju officially requested the Ministry of Land, Infrastructure and Transport to expand the Gwangsan IC to Donggwangju IC section in 2009. A meeting of relevant government agencies chaired by the Office for Government Policy Coordination brought the project into focus in 2012, and the Korea Development Institute (KDI) completed the preliminary feasibility study in 2013.
Location map of Honam Expressway Gwangju section expansion project (Donggwangju IC~Gwangsan IC). This project aims to expand the 11.2 km section from Donggwangju IC to Gwangsan IC from 4 lanes to 6 lanes, divided into sections 1, 2, and 3, with completion targeted by the end of 2029. Provided by Jeonnam Gwangju Integrated Special City.
View original imageThe original plan called for expanding the 10.8 km section from Gwangsan IC to Donggwangju IC from four lanes to six, as well as the construction of an access road at Yongbong IC, soundproofing facilities, and improvements to aging bridges. The benefit-to-cost ratio (B/C) was 0.96, which fell short of the usual standard, but the project was deemed appropriate to move forward thanks to a comprehensive evaluation of policy effects and regional balanced development (AHP 0.517).
Project Passed Feasibility, but Construction Did Not Start: Years Lost to Design and Negotiations
Even after passing the preliminary feasibility study, construction did not immediately begin. In 2015, the city of Gwangju and Korea Expressway Corporation entered into a cost-sharing agreement, but primary design, detailed design, and repeated reviews of the project's feasibility dragged on for years. According to documents from the Gwangju City Council, the primary design and feasibility review took place from 2015 to 2018, while detailed design and additional feasibility reviews continued from 2019 to 2022, with the final design only completed in 2023.
During the prolonged delays, the scale of the project ballooned. Efforts to reduce noise in residential neighborhoods led to the addition of 12 new soundproof tunnels and expanded soundproofing plans, prompting further design changes. Combined with increases in material and construction costs, the total project budget swelled from the initial 276.2 billion won to 793.4 billion won.
Groundbreaking ceremony for the Honam Expressway Donggwangju IC to Gwangsan IC expansion project held on September 22 last year in the garden of the National Gwangju Museum, Buk-gu, Gwangju. Provided by Jeonnam Gwangju Integrated Special City
View original imageBy the time construction finally began in September last year, the project had been adjusted from its original scope to cover an 11.2 km section between Donggwangju IC and Gwangsan IC. The construction is now divided into three segments—Donggwangju IC, Yongbong IC, and Seogwangju IC—with a final completion target set for the end of 2029.
The project encountered further complications just before groundbreaking. Last year, the city of Gwangju, citing financial constraints, requested additional central government funding from the national government instead of maintaining the status quo regarding local cost-sharing. As a result, budget funds previously included in the government’s supplemental budget were cut, raising concerns about possible disruption to the project. After gathering public feedback, the city decided to proceed as planned, leading to the start of construction in September that year. However, as Jeonnam Gwangju Integrated Special City launched, concerns over the local share of the funding have surfaced again, and negotiations over how to split the financial burden are ongoing.
Construction Ongoing: New Variables from Cultural Heritage and Local Funding Burdens
As of July 2026, construction remains underway. According to Jeonnam Gwangju Integrated Special City and Korea Expressway Corporation, as of the second week of July, the overall progress rate is 2.02%. By segment: Section 1 is at 1.73%, Section 2 at 2.19%, and Section 3 at 2.15%. Preparatory work, such as relocating obstructing trees, is underway at the site, along with preparations for full-scale civil engineering operations.
However, a new variable emerged this year during the cultural heritage survey within the construction zone. Artifacts and relics dating from the Bronze Age to the Joseon Dynasty were discovered and are currently undergoing detailed archaeological excavation. As this survey is a legally mandated process, there remains a possibility that the results could impact the timeline of certain segments.
The Jeonnam Gwangju Major Transition Planning Committee held a Gwangju regional work sharing meeting on the 23rd of last month at the Bitgaram Complex Culture and Sports Center in Naju, Jeonnam, and took a commemorative photo with the heads of the five autonomous districts of Gwangju and the leaders of Damyang and Jangseong counties. Photo by Bohyun Song
View original imageNegotiating the structure for financial cost-sharing remains a major uncertainty for the timeline ahead. During the transition committee's work-sharing meeting last month, Min Hyungbae, mayor of Jeonnam Gwangju Integrated Special City, indicated that it was necessary to re-examine the funding plan for the nearly 400 billion won in local contributions required for the Honam Expressway expansion project.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Regarding this, representatives from Jeonnam Gwangju Integrated Special City and the transition committee clarified that Mayor Min’s suggestion to review the plan does not mean the project will be abandoned. Rather, due to the large scale of the project budget, the intention is to more thoroughly review the financial burden and funding plan.