Reviewing Power Plans for the Southwest Semiconductor Cluster
Insufficient Renewable Energy... Need for Both Nuclear and LNG Raised
"Supplying 6.3GW of Power Within This Administration's Term Is Virtually Impossible"

At a semiconductor strategy forum hosted by the People Power Party, experts concluded that it is realistically difficult to establish the power infrastructure for the southwestern semiconductor cluster—an initiative being promoted by the Lee Jaemyung administration—within its current term.


On July 9, Kim Kyunggi, Senior Vice President of the Korean Society of Semiconductor & Display Technology, expressed this view at the "Semiconductor Future and Survival Series Discussion," co-hosted by Assemblyman Joo Ho-young and the People Power Party Semiconductor and AI Advanced Industry Special Committee. Kim stated, "Although the Lee Jaemyung administration has pledged to complete the southwestern semiconductor cluster within its term, there is a mismatch in the timeline when examining the power supply plan. The plan to finish this project within the current administration is not realistic."


Joo Ho-young, a member of the People Power Party, is delivering a greeting at the "Semiconductor Future and Survival Series Discussion," co-hosted by the People Power Party Semiconductor and AI Advanced Industry Special Committee. Provided by Yonhap News Agency

Joo Ho-young, a member of the People Power Party, is delivering a greeting at the "Semiconductor Future and Survival Series Discussion," co-hosted by the People Power Party Semiconductor and AI Advanced Industry Special Committee. Provided by Yonhap News Agency

View original image

According to Kim, operating the four planned semiconductor plants in the southwestern region will require at least 6.3 GW of power. This is equivalent to the output of 4.5 large-scale nuclear power plants, or the electricity consumed by six large cities with a combined population of about 1.3 million people. He pointed out, "If you include not only the southwestern cluster but also the existing Yongin cluster, partner companies, and materials, parts, and equipment (so-called 'SoBuJang') firms, the actual power demand becomes much greater."


While some have claimed that abundant renewable energy resources in the southwest, such as offshore wind, can be utilized, Kim argued that this is also not a realistic solution. He stated, "The average solar output in Honam is 1.8 GW, which is less than 30% of the cluster’s constant power demand. In addition, only about 1% of the permitted offshore wind facilities are currently in commercial operation."


He continued, "An energy portfolio that incorporates not only renewable energy but also nuclear power and LNG is necessary. Nuclear plants take 7 to 8 years to build, and SMRs require even more time due to safety reviews. LNG is relatively faster, but it conflicts with carbon neutrality goals."


Assemblyman Joo Ho-young, who hosted the discussion, also commented, "This appears to be a government-driven initiative rather than one autonomously pursued by the private sector, which is concerning. Starting with the issue of power, we will hold a series of forums on water, workforce, and the industrial ecosystem to thoroughly review this national project."


Assemblyman Ko Dongjin of the People Power Party added, "In semiconductors, it is a contest over people, water, and electricity. This is not about opposing Gwangju, but rather about the need to thoroughly verify why this particular region is being chosen." He continued, "Although there is a lot of renewable energy in Honam, providing a stable 24-hour power supply is impossible. In the end, stable base-load power sources such as nuclear and LNG must be secured." He further emphasized, "Decisions about industrial development must be made and judged strictly by businesses themselves."


In contrast, the government stated its intention to proceed without delay by simultaneously investing in the southwestern region and developing the Yongin cluster. Ahn Hongsang, Director of the Semiconductor Division at the Ministry of Trade, Industry and Energy, said, "No site can meet 100% of a company's desired conditions. Once a company decides to invest, the government’s role is to support the infrastructure—such as power and water—so that plants can operate on schedule."



He further explained, "The government's broader strategy is to expand semiconductor manufacturing bases nationwide and spread the ecosystem throughout the country, alongside investment in the southwestern region."


This content was produced with the assistance of AI translation services.