James Park, CEO of Lotte Biologics, Holds Press Conference

'GMP-Ready' Achieved Six Months Ahead of Schedule

Global Order Competitiveness Enhanced Through 'Dual-Site' System

Lotte Biologics has completed the construction of its Songdo Bio Campus Plant 1 and obtained approval for its use, effectively finalizing the establishment of a 'dual-site' production system connecting the United States and Korea. As a result, the company achieved 'GMP-ready' (completion of facilities and quality systems for pharmaceutical production) status six months ahead of its original schedule.


James Park, CEO of Lotte Biologics, is speaking at a press conference held in San Diego, USA, on the 23rd (local time). Lotte Biologics

James Park, CEO of Lotte Biologics, is speaking at a press conference held in San Diego, USA, on the 23rd (local time). Lotte Biologics

View original image

James Park, CEO of Lotte Biologics, held a press conference on the 23rd (local time) during the 2026 BIO International Convention (BioUSA) in San Diego, USA. He stated, "Completing the construction of Songdo Plant 1 ahead of schedule is significant," adding, "With the Syracuse Bio Campus and Songdo Plant 1 as our foundation, we have secured production capabilities at a global top-10 level in the CDMO (Contract Development and Manufacturing Organization) market. We will further strengthen our business competitiveness going forward."


At the press conference, Lotte Biologics shared key business updates, including the completion and approval of Songdo Bio Campus Plant 1, and outlined its future growth strategy. During the BioUSA exhibition, the company operated an exclusive booth and held in-booth presentations to showcase its process development and manufacturing capabilities.


Songdo Plant 1 was completed six months earlier than the GMP-ready timeline announced at the groundbreaking ceremony in 2024. The company explained that this was over two years faster than the typical construction period for biomanufacturing facilities. Lotte Biologics described this as a case demonstrating their execution ability to swiftly carry out global CDMO projects while stably establishing large-scale production facilities.


To achieve GMP-ready status, the company plans to sequentially conduct commissioning, establish quality management systems, and carry out validation procedures for production processes and equipment. Once these processes are completed, commercial production will begin. Lotte Biologics is currently in discussions with various global potential clients, who are also conducting on-site visits.


Once Songdo Plant 1 is fully operational, Lotte Biologics will complete its dual-site system, with Syracuse in the United States and Songdo in Korea as its two main hubs. The company plans to leverage the quality competitiveness and operational expertise it has accumulated at the Syracuse Bio Campus, combined with the large-scale production capabilities in Songdo, to meet the commercial production needs of global clients.



Order performance is also becoming visible. Lotte Biologics has announced a total of four new orders so far this year. The company explained that its CDMO capabilities and customer responsiveness, built upon the Syracuse Bio Campus, have led to these orders. Lotte Biologics expects that as the Songdo Campus becomes fully operational, its ability to respond to large-scale commercial production demands will further strengthen its order competitiveness.