2nd Public Housing Supply Task Force Meeting
"Proactively Addressing Delays in Housing Supply"

Kim Itak, First Vice Minister of the Ministry of Land, Infrastructure and Transport, stated on the 24th, "The target of starting construction on 11,000 public housing units in the Seoul Metropolitan Area in the first half of the year has been achieved as planned," and added, "We will thoroughly manage the process to ensure that the construction of a total of 62,000 units by the end of the year and more than 70,000 units next year will also proceed according to plan."


On this day, Vice Minister Kim held the "2nd Meeting of the 2026 Public Housing Supply Task Force" at the joint housing supply task force meeting room of the Ministry of Land, Infrastructure and Transport and LH in Yongsan-gu, Seoul, together with representatives from four major public corporations: Korea Land & Housing Corporation (LH), Seoul Housing & Communities Corporation (SH), Gyeonggi Housing & Urban Development Corporation (GH), and Incheon Housing & City Corporation (iH).


Vice Minister Kim said, "We will identify and resolve causes of delay at each stage of the project as early as possible and closely collaborate with relevant agencies." He further requested, "Please accelerate the supply process even further so that the public can quickly experience tangible results."


Kim Itak, First Vice Minister of the Ministry of Land, Infrastructure and Transport, is speaking at the 2nd meeting of the Metropolitan Public Housing Supply Task Force held on the 24th in the task force meeting room of the joint Ministry of Land, Infrastructure and Transport and LH in Yongsan-gu, Seoul. Ministry of Land, Infrastructure and Transport

Kim Itak, First Vice Minister of the Ministry of Land, Infrastructure and Transport, is speaking at the 2nd meeting of the Metropolitan Public Housing Supply Task Force held on the 24th in the task force meeting room of the joint Ministry of Land, Infrastructure and Transport and LH in Yongsan-gu, Seoul. Ministry of Land, Infrastructure and Transport

View original image

The government has shifted its housing supply monitoring standard from 'permit approval' to 'construction start' to expedite actual occupancy for home seekers. Typically, even after a project receives permits, delays in land compensation or conflicts over construction costs often mean it takes over five years for residents to move in. For those without a home who urgently need housing, simply approving permits is insufficient to stabilize the market. In contrast, once a project reaches the construction start stage, occupancy can usually occur within two to three years, sending a clear signal of real supply. The Ministry of Land, Infrastructure and Transport also plans to proactively prevent bottlenecks from the land compensation and site preparation stages to achieve next year's goal of starting construction on 70,000 units.


In fact, over the past few years, public housing supply in the Seoul Metropolitan Area has hit record lows. While the number of public housing construction starts in the region reached 65,000 units in 2020, it dropped to 41,000 units in 2021, 20,000 units in 2022, and then plummeted to just 16,000 units in 2023. If the goal of starting construction on 62,000 units by the end of the year is achieved through measures such as streamlining administrative procedures, the supply level will return to that of 2020 for the first time in six years. The Ministry of Land, Infrastructure and Transport plans to closely monitor progress each month and pursue parallel administrative measures to ensure that the year-end construction start target is met without setbacks.



Meanwhile, on the same day, the Presidential Office also emphasized the need to expand housing supply. Kim Yongbeom, policy chief at the Presidential Office, stated at the Kwanhun Forum, "We need to get on with building houses," and added, "The central government, Seoul Metropolitan Government, and other stakeholders need to work together."


This content was produced with the assistance of AI translation services.