Maximum Power Demand to Reach 138.2GW by 2040, Up 37% from Last Year
Nuclear Share Needs to Rise from 30% to 35%

"Two Large Nuclear Plants Not Enough for AI Era... Need 20 More in the Long Term" View original image

With the final decision on new nuclear power plant candidate sites, domestic nuclear construction is back on track. The government plans to build two large nuclear power plants in Yeongdeok, North Gyeongsang Province, and one small modular reactor (SMR)—the country’s first commercial SMR—in Gijang, Busan. However, both the nuclear industry and academia argue that “this decision is only the beginning,” and insist that, to meet the rapidly growing electricity demand in the era of artificial intelligence (AI), at least three additional reactors in the short term and more than 20 in the long term will be necessary.


New Nuclear Clock Restarts After 15 Years

On June 17, the Site Selection Evaluation Committee for New Nuclear Plants selected Yeongdeok County, North Gyeongsang Province, and Gijang County, Busan, as candidate sites for new nuclear construction under the 11th Basic Plan for Electricity Supply and Demand (2024–2038).


In Yeongdeok, two large reactors with a capacity of 1.4 GW each will be built, with completion targeted for 2037 and 2038, respectively. In Gijang, the country's first commercial SMR is scheduled for completion in 2035. This is the first time since 2011 that sites for new nuclear plants have been confirmed.


At that time, the government designated Yeongdeok and Samcheok as candidate sites for new nuclear facilities, but the combination of a phase-out nuclear policy, local opposition, and changes in electricity policy led the projects to stall for an extended period. The significance of the current decision lies in the fact that, after about 15 years, the previously halted new nuclear construction process has resumed. The Evaluation Committee emphasized the necessity of new nuclear construction, stating, "Ensuring a stable electricity supply and securing national competitiveness are essential tasks for future generations."


AI Drives Power Demand... Up to 37% Increase by 2040

However, the two reactors in Yeongdeok and one SMR in Gijang are projects already included in last year’s 11th Basic Plan for Electricity Supply and Demand. Industry attention is now shifting toward the 12th Basic Plan for Electricity Supply and Demand (2026–2040), currently being formulated by the Ministry of Climate, Energy, and Environment. According to provisional forecasts from the ministry and the 12th Plan’s General Committee, peak power demand in 2040 is expected to reach 138.2 GW in the high-growth scenario.


This is approximately a 37% increase from last year’s peak demand of 100.9 GW. Annual electricity consumption is also projected to reach 694.1 TWh, up 26.3% from last year.


The key variable driving increased electricity demand is AI. The government also cites the proliferation of AI data centers, the creation of semiconductor clusters, and industrial electrification as major drivers of demand growth. In particular, AI data centers require a stable, 24-hour electricity supply.


Both the nuclear industry and academia argue that it will be difficult to resolve output volatility and grid constraint issues solely through the expansion of solar and wind power, stressing the need to secure large-scale baseload power sources.


"At Least Three Nuclear Reactors Should Be Included in the 12th Plan"

The nuclear sector believes that the two new reactors already included in the 11th plan will not be sufficient to meet future demand.


The Council of Professors for Rationalization of Energy Policy held a press conference titled “Energy Policy: A Matter of Survival” on June 15, arguing that additional nuclear construction plans must be included in the 12th plan.


Shim Hyungjin, professor of nuclear engineering at Seoul National University, stated, “To achieve carbon neutrality by 2050, ensure energy security, and enhance industrial competitiveness, the share of nuclear power generation must be increased from the current level of 30% to 35%.” He proposed that the 12th plan should include at least three additional large reactors and at least two additional SMRs.


He also presented an analysis showing that, in the long term, construction of as many as 20 additional large reactors and 12 SMRs will be necessary. An industry official commented, “Even if the two Yeongdeok reactors are built, they will not begin producing electricity until the late 2030s at the earliest. Given projections for a 37% increase in power demand by 2040, deciding on additional nuclear construction now is by no means a luxury in terms of schedule.”


The Beginning of Nuclear Expansion... Remaining Challenges: Public Acceptance and Waste

Selecting nuclear sites means facing, once again, issues of local opposition and spent nuclear fuel management. As the construction of new nuclear plants is a long-term project taking more than ten years, from site selection to permits, groundbreaking, and completion, it will be difficult to accelerate the process without social consensus.


Nevertheless, the nuclear industry and academia believe that the 12th plan will effectively mark a turning point in electricity policy for the AI era. While the two Yeongdeok reactors are the result of the 11th plan, they argue that decisions on additional nuclear construction must be made now to respond to post-2040 power demand.



An industry official said, “This selection of Yeongdeok is not the end but the beginning of nuclear expansion. Considering the electricity demand from AI data centers and advanced industries, the extent to which the 12th plan incorporates new nuclear plants and SMRs will be the central issue for future electricity policy.”


This content was produced with the assistance of AI translation services.