The transfer center development project, one of the key initiatives in the redevelopment of Busan Port North Port, has ultimately entered a phase of contract termination.


Busan Port Authority (BPA) has decided to terminate the land sale contract, citing repeated contract violations by the developer PQ Construction and the unresolved height difference (level gap) issue, drawing attention to whether the project can be normalized.


Busan Port Authority announced on June 16 that it plans to notify PQ Construction of the termination of the land sale contract for the transfer center site. BPA determined that maintaining the contract was no longer possible since the developer had continued unauthorized construction in violation of the district unit plan for an extended period and failed to respond sincerely to requests for a written commitment to resolve the level gap issue.


The core of the controversy lies in the height difference between the transfer center and adjacent public spaces. BPA explained that it had demanded a solution to the level gap for more than a year and a half to ensure public views and public interest, but PQ Construction repeatedly stated only that it was in the process of design modification and continued with the construction.


In fact, PQ Construction did submit a revised design plan to address the level gap in April, but BPA believes that as illegal construction continues, the higher the construction progress rate, the more difficult it becomes to resolve the problem.


The conflict between the two sides has deepened recently during the process of submitting the written commitment. BPA requested the submission of a written commitment addressing the level gap and limiting the scope of construction twice last month, but was refused, and only received the document on June 15 after issuing a final notice.


However, BPA holds the position that this written commitment is effectively not valid. The initially requested construction suspension standard, "only underground construction may proceed," was omitted, and additional language was inserted to suggest that the level gap resolution was at BPA's request, thus attempting to dilute the developer's responsibility.


Furthermore, BPA pointed out that clauses refusing to reject the resolution of the level gap on the grounds that future design modification would be difficult, as well as a provision agreeing to contract termination in the event of non-fulfillment, were both omitted, suggesting that the developer intended to evade responsibility.


Additionally, the developer failed to pay approximately 3.1 billion won in delay compensation despite missing the development deadline, and has not submitted the demolition performance guarantee insurance policy requested since the end of last year, failing to fulfill contractual obligations. This is also cited as a reason for the contract termination.


A BPA official stated, "Despite multiple requests for corrective action to resolve the level gap issue, the developer did not demonstrate a genuine intention to comply, and various contract violations have accumulated," adding, "We determined that it is no longer possible to proceed with the project in a normal manner given the breakdown of mutual trust."



As the transfer center project, which has been promoted as a symbolic facility of the North Port redevelopment, faces a significant turning point, there is growing attention on potential legal actions and plans to relaunch the project.

Busan Port Authority.

Busan Port Authority.