Results of Regular Audit by the Board of Audit and Inspection
Unqualified Subcontractors Conducted 4.3 Billion Won Battery Construction
12 Out of 18 Airport Area Development Projects Found Economically Unviable
“Deficiencies in Both Revenue

During a regular audit of Incheon International Airport Corporation, the Board of Audit and Inspection discovered that the corporation had inappropriately reduced rental fees for commercial facilities such as duty-free shops, resulting in more than 150 billion won in undercollected rent. In addition, some airport facilities were found not to meet current seismic standards, yet were neither properly assessed nor reinforced. The audit also revealed that, in a battery installation project for emergency power supply, an unqualified company effectively received a turnkey subcontract worth 4.3 billion won and carried out the construction.


Yonhap News

Yonhap News

View original image

On June 15, the Board of Audit and Inspection released the main findings of its "Regular Audit of Incheon International Airport Corporation," announcing that it had identified a total of 14 violations or improper practices and had taken actions including calls for disciplinary measures and corrections.


The area with the largest financial impact was the adjustment of rental fees for commercial facilities in Terminal 2 (T2). From June to December 2023, the airport corporation selected five duty-free operators to run seven duty-free concessions in Terminals 1 and 2, as well as operators for food, beverage, and convenience store concessions.


At that time, the airport corporation created an integrated business right for Terminals 1 and 2, considering the T2 expansion and airline relocations, so that if sales at one terminal decreased, they could be offset by increases at the other. The rental fees were determined using a "per-passenger rental fee" method, multiplying the number of departing passengers at all terminals by the operator's proposed fee per person. Special terms were also included to prevent rent adjustments even if passengers or flights shifted between terminals.


However, in December last year, after the opening of new stores in T2, the airport corporation regarded these as temporary stores, citing the lack of increased passenger numbers due to airline relocations. As a result, it charged sales fees lower than the per-passenger rates. The Board of Audit and Inspection found that, due to this measure, 8 operators running 11 stores were undercharged a total of 151.7 billion won in rent over a 13-month period from December 2023 to January 2026, compared to the amounts stipulated in the original contracts.


Additionally, in January of this year, the airport corporation allowed three duty-free operators to replace the remaining cash security deposit with a surety bond, which resulted in a loss of about 3.27 billion won in interest income for one year. The Board of Audit and Inspection warned the president of the airport corporation to ensure that rental fees are not improperly charged and that the method of paying security deposits is not arbitrarily changed in a way that results in lost revenue, stressing the need for thorough management of related work.


Profitability reviews were also found to be insufficient in land development projects around the airport. The airport corporation developed and leased 10 million square meters of land near the airport for hotels, recreation, and office facilities through private investment, but applied uniform lease periods and rental calculation methods without conducting economic feasibility studies on the nature or profitability of the facilities.


All seven currently leased facilities had lease periods of 50 years and rental fees set at 5% of the publicly announced land value. During the audit, the airport corporation's own analysis revealed that, of 18 hotel, recreation, and office facilities, 12 were not economically viable, as their lease income failed to meet even the opportunity cost of not leasing the land.


The demolition conditions for facilities were also found to be unfavorable to the airport corporation. Of eight facilities contracted to be demolished by the airport corporation upon lease expiration, six would have been more economically advantageous if the private operator had transferred the facility free of charge. Some office facilities were found to have been changed and used as unregistered lodging establishments, contrary to the implementation agreement, yet the airport corporation failed to address these violations.


Poor safety management was also revealed. From 2018 to 2023, the airport corporation signed five electrical construction contracts totaling 6.5 billion won with five companies for the purchase and installation of batteries used in emergency power supply systems. These contracts involved both goods procurement and construction, meaning only registered electrical contractors could bid, and subcontracting was generally prohibited.


However, the Board of Audit and Inspection found that the contractors had effectively subcontracted a total of 4.3 billion won in construction to unregistered companies, which repeatedly performed the work, yet the airport corporation approved project completion without taking any action. The difference between the primary contract and the subcontracts totaled 2.2 billion won. Some batteries were brought in and installed without Korean Industrial Standards inspection or test reports.


The Board of Audit and Inspection instructed the president of the airport corporation to prepare measures such as prosecuting the primary contractors and unqualified subcontractors who entered into illegal subcontracting agreements, and restricting their participation in future bids. It also called for disciplinary measures, at least a reprimand, against those responsible for improperly handling contract management and project completion work.


The seismic safety management of airport facilities was also called into question. As a disaster management agency, the airport corporation is required to assess the seismic performance of airport facilities, which are designated as national key infrastructure, and implement reinforcement measures. Following the Gyeongju and Pohang earthquakes, standards for seismic design and target structures were strengthened, making a systematic evaluation of the 212 existing airport facilities necessary.


However, the airport corporation conducted seismic performance evaluations only for 40 facilities that did not have seismic design at the time of completion. The remaining 142 facilities, which were designed to be earthquake-resistant at the time, were not reassessed for compliance with current standards for up to 25 years after their completion.



With the cooperation of the Korea Infrastructure Safety and Technology Corporation, the Board of Audit and Inspection conducted a preliminary evaluation of 23 airport facilities that had been completed for over 20 years, finding that 13 of them were at risk of total or partial collapse or serious damage in the event of a magnitude 6.1 to 6.5 earthquake. The Board of Audit and Inspection instructed the airport corporation to prepare plans to enhance the seismic performance of these 13 facilities, including Substation B, and to establish and implement a systematic seismic performance evaluation plan for all existing airport facilities.