Gwangju Military Airport Relocation: City Considers Reducing Construction Period by Up to Four Years
Gwangju Considers Design-Build Turnkey Approach
City in Talks with Government on Turnkey Method Adoption
Appropriateness to Be Reviewed During Basic Planning Stage
As the area around Mangun-myeon in Muan County, South Jeolla Province, has been designated as a preliminary candidate site for the relocation of the Gwangju military airport, the city of Gwangju is considering introducing a design-build (turnkey) bidding method to shorten the overall project timeline. By proceeding with design and construction simultaneously after the final site is determined, the city aims to accelerate the project, and is currently discussing this approach with relevant government ministries.
According to the city of Gwangju on June 15, the city is considering the turnkey method as a way to reduce the construction period for the military airport relocation project, and is in ongoing consultations with related ministries such as the Ministry of National Defense and the Ministry of Economy and Finance.
Pilots from the 1st Fighter Wing in Gwangsan-gu, Gwangju, are landing after completing flight training with combat aircraft. [Photo by 1st Fighter Wing]
View original imageThe Gwangju military airport relocation project is being promoted under a special law, with the city of Gwangju constructing a new military airport and donating it to the Ministry of National Defense in exchange for receiving the old site, which will then be developed. This is known as the "donation for transfer" method.
Currently, the area around Mangun-myeon in Muan County, South Jeolla Province, has been designated as a preliminary candidate site. The final relocation site will be determined through a review of candidate sites, the establishment of support plans, and a resident referendum.
The city of Gwangju believes that, compared to the traditional method of sequentially carrying out basic design, detailed design, and construction after the relocation site is finalized, the turnkey method—which allows design and construction to proceed in parallel—will be more effective in speeding up the project. The city expects that this could shorten the construction period by up to about four years.
Choi Moonseon, head of the Gwangju City Military Airport Relocation Project Team, said, "While consulting with government ministries, we were looking for ways to expedite the airport relocation, and proposed the turnkey method as a means to reduce the project duration." He continued, "It is still at the conceptual stage," adding, "Ultimately, whether the turnkey method is appropriate will be discussed and decided during the process of establishing the basic plan."
If the relocation site is finalized in the second half of this year, the city of Gwangju aims to begin the process of establishing the basic plan within the same period. It typically takes about 18 months to two years to establish the basic plan.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
However, separate from efforts to shorten the project period, securing financial resources remains a challenge. Since the military airport relocation project is being carried out under the donation for transfer method, the city of Gwangju must initially bear the construction costs for the new military airport. Once the relocation site is finalized, the city plans to further specify the project method and financial procurement measures, and then finalize the overall direction of the project after consultations with the government.
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.