EP Phase 2 Orders Split Among LS Cable, Taihan Cable, and Iljin Electric
Fiercer Competition Expected for Future "West Coast Energy Expressway" Projects

The direction of the East Coast–East Seoul high-voltage direct current (HVDC) underground cable supply project—a massive power infrastructure initiative commissioned by Korea Electric Power Corporation—has been determined by a split order among the "big three" domestic cable manufacturers. This outcome reflects the commissioning party’s intention to ensure supply chain stability and reduce the risks associated with long-term project execution.


According to the cable and energy industry on June 11, the Contract Division of KEPCO’s Win-Win Procurement Office closed the bidding for the cable purchase for the "500kV East Coast–East Seoul HVDC EP Phase 2 Underground Transmission Project," with a total project cost of KRW 300 billion, on June 9 and selected the successful bidders. As a result of the final bid opening, the core power line section, Section 1, was awarded to LS Cable; Section 2 went to Taihan Cable; and Section 3, which involves the 70kV-class neutral line, was assigned to Iljin Electric.

An LS Cable employee is inspecting the construction site of the "East Coast - Singapyeong" where the 500kV-class HVDC cable is being installed. LS Cable

An LS Cable employee is inspecting the construction site of the "East Coast - Singapyeong" where the 500kV-class HVDC cable is being installed. LS Cable

View original image

The East Coast–East Seoul transmission network is a key national infrastructure that directly transports power generated by nuclear and thermal power plants, as well as large-scale renewable energy complexes in the East Coast area, to the Seoul metropolitan region, where electricity consumption is extremely high. For manufacturers, this project is not only an opportunity to achieve significant sales but also to secure a critical domestic track record that will be essential for future bids in the global high-voltage transmission market. As a result, the industry engaged in fierce competition for the orders.


KEPCO stated, "If too much volume is concentrated with a single company, unexpected bottlenecks or risks may arise. By splitting the contracts by section, we can accelerate each individual construction process and manage the overall supply chain more stably. That is why we applied the distributed bidding principle again for this phase, just as we did for EP Phase 1."


In the previous "East Coast–Singapyeong HVDC" (EP Phase 1) project, LS Cable secured the plus (+) and minus (-) power line cables, while Iljin Electric supplied the neutral line section.


The most notable result in this Phase 2 bid is Taihan Cable’s first entry into the main project. Having made large-scale investments in its submarine cable factory in Dangjin, South Chungcheong Province, and devoted itself to developing 500kV-class products, Taihan Cable has now achieved its long-anticipated first major HVDC project record in the domestic market by winning Section 2. With LS Cable solidifying its position as a market leader by winning Section 1, both companies have proven their technological capabilities. As a result, competition between the two for future large-scale national transmission projects, such as the "West Coast Energy Expressway" expected to be commissioned next year, is expected to intensify further.


The recently closed EP Phase 2 project is being conducted as a conditional installation purchase, under which the suppliers are responsible for everything from material production to on-site laying and installation. The total length of the combined power and neutral lines for all three sections is approximately 256 kilometers. By specification, Section 1 (500kV) is 85.508 kilometers, Section 2 (500kV) is 85.559 kilometers, and Section 3 (70kV) is 85.328 kilometers.



The three cable companies that secured bid rights are expected to submit detailed cost breakdowns to KEPCO soon, finalize the main contracts, and then begin full-scale cable mass production. KEPCO stated that it plans to complete the final contract signing within this month and will promptly proceed with subsequent technical approval procedures, including official design review and product specification examination.