Investigation of Presumed Ignition Point Conducted for Nearly Seven Hours with Bereaved Families Present

The police have begun investigating the cause of the explosion at the Hanwha Aerospace Daejeon Plant, which resulted in seven casualties, including five deaths.


On the 1st, police and fire officials are handling the aftermath of an explosion accident that caused casualties at Hanwha Aerospace Daejeon plant in Yuseong-gu, Daejeon. Photo by Yonhap News Agency

On the 1st, police and fire officials are handling the aftermath of an explosion accident that caused casualties at Hanwha Aerospace Daejeon plant in Yuseong-gu, Daejeon. Photo by Yonhap News Agency

View original image

According to the Daejeon Metropolitan Police Agency, a joint inspection was conducted at the accident site on June 2 from 10:00 a.m. to around 4:40 p.m., lasting nearly seven hours, together with five related organizations: the fire department, the National Forensic Service, the Ministry of Employment and Labor, and the Korea Occupational Safety and Health Agency. A total of 34 personnel took part in the inspection, and bereaved family members were also present.


At approximately 10:59 a.m. the previous day, an unexplained explosion occurred in the washing room of Building 56 at the Daejeon Plant, resulting in the deaths of five workers and serious or moderate injuries to two others.


Hanwha explained that, at the time, workers were cleaning gunpowder residue from equipment used to produce propulsion units such as launch vehicles.


The police checked the condition of the site and investigated the presumed ignition point. Using heavy machinery, they removed parts of the collapsed wall and steel shielding, then identified the area believed to be the source of ignition.


It was reported that the authorities focused on determining whether flammable substances were present at the scene. However, as most of the materials had already burned, it was difficult to confirm this with the naked eye.


The police plan to send partially burned debris collected from the presumed ignition point to the National Forensic Service for a detailed examination.


There were no closed-circuit (CC)TV cameras installed inside the building, but external CCTV footage has been secured.


It was reported that the company had postponed installing internal CCTV cameras because it had not yet obtained consent for the protection of employee personal information.


The police stated that although part of the building was damaged by the explosion, there is currently no significant risk of collapse.


To identify the deceased, the police requested DNA analysis from the National Forensic Service the previous day, using samples from both bereaved family members and the deceased.


An autopsy was also conducted in the afternoon of June 2.


The Daejeon Metropolitan Police Agency's special investigation team questioned Supervisor A, who returned from the hospital after receiving minor injuries, and Employee B, who was off duty on the day of the accident, as witnesses.


The washing room work team initially consisted of eight members. Supervisor A was in charge of safety-related maintenance for the team, while Employee B, who joined the company together with two contract workers who died in the accident, was a new employee.


The police reportedly questioned them about the circumstances before and during the accident, the overall work processes in the washing room, the composition of cleaning agents, and the existence and compliance with safety guidelines.



Separately from the joint inspection, the police also obtained some relevant materials from Hanwha in the form of voluntary submissions, to verify the cause of the accident and the company's safety management practices.


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.

Today’s Briefing