[Interview] "Taean to Become a Hub for Offshore Wind O&M and Renewable Energy Industry" ... Jungbok Lee, President of Korea Western Power
Responding to Coal Plant Closures by 2037
Generation of 560,000 Square Meters of Idle Land and New Infrastructure
Expanding Profit-Sharing Models for Local Communities
"Utilizing the hinterland port and cable landing points is not simply a matter of recycling facilities. It should be about transforming Taean into a hub for offshore wind operation and maintenance, as well as for the renewable energy industry."
Jungbok Lee, President of Korea Western Power (pictured), stated in a recent interview with The Asia Business Daily, "The decommissioning of coal-fired power plants is not just a change in power generation sources; it affects employment, partner companies, port cargo volumes, and local tax revenue," emphasizing the complexity of the issue.
The Taean Power Complex of Korea Western Power closed its first coal-fired unit in December 2025, and a total of eight coal-fired power plants are scheduled for closure by 2037. In response, the company is actively fostering its renewable energy business to address the coal phase-out and strengthen future growth engines.
In April 2026, the company restructured its renewable energy division, expanding from four departments under a single office to five departments across two offices, and added 30 dedicated personnel. As a result, the workforce for renewable energy operations increased from 131 to 161 employees.
Korea Western Power has also established a mid- to long-term roadmap to expand its renewable energy capacity to 3.9GW by 2030 and 13.9GW by 2040. The focal point of this strategy is Taean, where the company’s headquarters is located.
President Lee explained, "By the end of 2037, when the eighth unit of the Taean coal-fired power plant is decommissioned, we expect to have about 560,000 square meters of idle land and related infrastructure. This will become a crucial asset for developing a hinterland port for offshore wind O&M and as a cable landing point."
However, simply having available land does not mean it can be immediately utilized. To bring electricity generated offshore to land, all conditions—including submarine cable routes, landing point locations, substation facilities, and available capacity in the existing transmission network—must be met. The port's ground must also be reinforced to a level that allows for maintenance vessels to dock, storage of equipment, and transportation of heavy cargo.
Additionally, various procedures such as environmental impact assessments, permits for the use of public waters, port utilization planning, and adjustments to fishing rights must be completed, and issues of community acceptance need to be addressed during these processes. Korea Western Power recently appointed 22 experts in the offshore wind sector as advisors and is actively working to resolve such complex issues.
Korea Western Power is currently pursuing energy transition projects totaling 2GW in the Taean region, including offshore wind and solar power. Particular emphasis is being placed on returning value to the community and sharing profits with local residents. The Iwonho floating solar power plant (43MW), completed in June 2024, will share a total of 9.5 billion won—an average of 480 million won annually—with residents over 20 years. The Haetdeulwon solar power plant, completed in September 2025, is operated as a profit-sharing model, distributing approximately 11 billion won, or an average of 550 million won per year, to residents through 2045.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
President Lee further explained, "Going forward, we plan to develop all 2GW of renewable energy projects in the Taean area—including the 1.4GW offshore wind projects (Taean, West Sea, and Gai), Iwon reclaimed land (500MW), and the Taean thermal power second ash disposal site (100MW)—as profit-sharing models."
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.