Ministry of Employment and Labor Approves Only Scaffolding Removal Plan

Seoul Metropolitan Government to Revise Demolition Plan After GPR Survey

The decision on whether to resume the demolition work on the Seosomun overpass, which was suspended due to concerns about further collapse, will be made on the afternoon of May 28 following a meeting between relevant agencies.

On the 26th, at the demolition site of the Seosomun overpass in Seodaemun-gu, Seoul, the deck collapsed, resulting in three fatalities and three injuries. Due to the risk of further collapse, restoration work has been delayed, causing disruptions to train operations including the Gyeongui-Jungang Line and KTX. May 27, 2026 Photo by Dongju Yoon

On the 26th, at the demolition site of the Seosomun overpass in Seodaemun-gu, Seoul, the deck collapsed, resulting in three fatalities and three injuries. Due to the risk of further collapse, restoration work has been delayed, causing disruptions to train operations including the Gyeongui-Jungang Line and KTX. May 27, 2026 Photo by Dongju Yoon

View original image

The Seoul Metropolitan Government stated, "At 9 a.m. today, a joint meeting with the Ministry of Land, Infrastructure and Transport, the Ministry of Employment and Labor, the police, and other relevant agencies was held to discuss demolition methods and safety measures." The city added, "Currently, a Ground Penetrating Radar (GPR) survey is being conducted to verify the safety of the demolition work."


At 3 p.m., a joint meeting of relevant agencies will be held, and at 4 p.m., the Ministry of Employment and Labor will review the work plan to finalize matters related to the resumption of construction, including the demolition method.


On May 26 at 2:33 p.m., a girder, a structural component serving as a main beam, collapsed at the Seosomun overpass, resulting in the deaths of three people, including construction officials who were conducting a safety inspection, and injuring three others. Due to the incident, trains that pass through the overpass are currently not operating.


Approval from the Ministry of Employment and Labor is required to resume the demolition. The ministry reviewed the demolition plan for the Seosomun overpass submitted by the Seoul Metropolitan Government the previous day, approving the plan for the removal of scaffolding, but requesting revisions to the girder demolition plan, citing insufficient safety measures.


An official from the Ministry of Employment and Labor stated, "The remaining scaffolding at the Seosomun site could be hazardous, so approval was granted to resume work in order to prevent a secondary accident," adding, "The demolition of the remaining sections will be reviewed separately based on a revised plan that considers structural safety."


The Seoul Metropolitan Government plans to submit a revised demolition plan for the girders and other components to the Ministry of Employment and Labor, based on the ongoing GPR survey. The ministry will review the revised plan and determine whether to approve the resumption of work later this afternoon.



If the project resumes, the city expects that dismantling the scaffolding, removing the slab and girder, and restoring the overhead train lines will take a total of 40 hours.