Kick-off Briefing for the Study to Be Held on May 28

Participation of Relevant Agencies in the Review Process

Assessment of Structural Stability and Identification of Reinforcement Methods

The Ministry of Land, Infrastructure and Transport, Seoul Metropolitan Government, and the National Railroad Corporation announced on May 28 that they will hold a kick-off briefing to launch a study examining the adequacy of reinforcement measures for construction errors found in the columns of the GTX Samseong Station section.


This study follows the results of an emergency on-site inspection by experts conducted over three days from April 6 to 8, during which it was suggested that a reputable professional institution should be commissioned to thoroughly review the structural analysis at each construction stage and the reinforcement methods.

View of the underground complex development site on Yeongdong-daero, a section of the GTX-A line in Gangnam-gu, Seoul. Photo by Yonhap News.

View of the underground complex development site on Yeongdong-daero, a section of the GTX-A line in Gangnam-gu, Seoul. Photo by Yonhap News.

View original image

Through this study, the authorities plan to verify structural performance via structural analysis, assess the structural stability in special situations such as earthquakes, identify the optimal column reinforcement methods, and establish maintenance measures. The aim is to derive more detailed and concrete results based on the previous expert on-site inspection. In particular, during the initial phase of the study, priority will be given to reviewing the feasibility of conducting reinforcement work alongside train operations and the impact of train vibrations on reinforcement performance.


The review will be conducted by a certified institution with expertise in civil engineering structures—the Korea Concrete Institute. All relevant organizations, including the Ministry of Land, Infrastructure and Transport, Seoul Metropolitan Government, National Railroad Corporation, SG Rail, Korea Railroad Corporation (KORAIL), and construction companies, will participate in the review process. The National Railroad Corporation stated, "Ownership of the facility will eventually be transferred to the state, SG Rail—the private operator for the GTX-A line—will handle operations, and KORAIL will be responsible for maintenance, which is why all related entities are participating in the review."


The Ministry of Land, Infrastructure and Transport, Seoul Metropolitan Government, and the National Railroad Corporation plan to comprehensively consider all necessary alternatives through this study and establish the optimal reinforcement measures. Starting next month, Seoul Metropolitan Government will conduct a detailed safety inspection, including structural analysis, over approximately three months to closely assess the stability of the existing structure.



The National Railroad Corporation stated, "The Ministry of Land, Infrastructure and Transport, Seoul Metropolitan Government, and the National Railroad Corporation will work to ensure that the detailed safety inspection of the structure being carried out by Seoul, and this review of reinforcement methods, complement each other."


This content was produced with the assistance of AI translation services.