AI and Data Center Boom Drives Surging Demand
Gas Turbine Prices Expected to Rise by 195%
"Equipment Procurement Determines Project Success"

A 380MW class gas turbine undergoing rated load performance testing at Doosan Enerbility. Photo by Yonhap News.

A 380MW class gas turbine undergoing rated load performance testing at Doosan Enerbility. Photo by Yonhap News.

View original image

The construction of the Jeju Combined Cycle Unit 3 project, promoted by Korea Midland Power, is now expected to be delayed by approximately three years from the original schedule due to setbacks in procuring key power equipment. The delay in securing main equipment such as gas turbines (GT) and steam turbines (ST) has pushed back the overall project timeline, emerging as a variable that could impact future electricity supply and demand.


According to the power generation industry on May 4, Korea Midland Power recently held a board meeting to review the 'Status Report on Facilities Reflected in the 12th Basic Plan for Long-term Electricity Supply and Demand,' and decided to adjust the completion date of Jeju Combined Cycle Unit 3 from 2027 to 2030. The reason for the adjustment was specified as 'delivery delays due to a surge in global demand for power equipment.' The entire project schedule has been reconfigured as the procurement of core equipment, such as turbines, has been delayed.


The Jeju Combined Cycle Unit 3 is a liquefied natural gas (LNG) combined cycle power plant project worth approximately 400 billion won, awarded to Korea Midland Power in September 2023. It has been considered a key facility for stabilizing electricity supply in the Jeju region. The plant employs a standard combined cycle format, consisting of one gas turbine and one steam turbine, and was originally scheduled for completion in 2027.


However, the situation has changed as supply bottlenecks in the global power equipment market have intensified recently. A Korea Midland Power official said, "Production slots for core equipment, especially gas turbines, have been booked years in advance by major manufacturers," adding, "For new orders, the lead time required is at least three to five years."


The main causes of the supply shortage are the proliferation of artificial intelligence (AI) and the increase in data centers. According to a recent report by energy consultancy Wood Mackenzie, the price of gas turbines is projected to rise by approximately 195% between 2019 and 2027. On a per-kilowatt basis, prices are expected to reach about $600. As of 2025, global demand for gas turbines is expected to be around 110 GW, but actual production capacity is only between 60 and 70 GW.


Additional demand for turbines is also being stimulated as gas-fired power generation is tasked with compensating for the intermittency that arises during the expansion of renewable energy. Market research firms forecast that over the next decade, the annual average growth rates for gas turbines and steam turbines will be 4.8% and 2.8%, respectively. This situation is significant because it is not simply a result of rising raw material prices, but rather a combination of surging demand and limited supply.

Key Power Equipment Shortage Pushes Jeju Combined Cycle Unit 3 Completion to 2030 View original image

The power generation industry has observed that the construction period for gas-fired power plants, which used to be about three to four years, is now increasing to six to seven years. The timing of securing equipment, rather than the pace of construction itself, is becoming the determining factor for the overall project schedule. Currently, it is known that for large gas turbines, the minimum time from order to actual delivery is three to five years, and for some projects, it can take more than six years. The production slots of major manufacturers have already been booked out for several years, making it necessary for new projects to prioritize equipment procurement from the earliest stages.


An industry official stated, "At this point, securing turbines is more critical than funding or permits. If equipment cannot be obtained, the project itself cannot even begin."


In major markets such as the United States and Asia, there are also cases where power generation projects are delayed or even canceled due to delays in securing turbines. In countries such as Vietnam and the Philippines, new LNG power projects are being delayed one after another because of the global gas turbine shortage, with some projects still in the initial stages without even securing turbine contracts.


For the Plant Yates gas-fired power project, which is being pursued by Georgia Power—a major electricity company responsible for power supply in the southeastern United States—gas turbines were ordered, but due to recent global supply shortages, the delivery period has stretched to as long as seven years, putting pressure on the entire project schedule.


The delay of Jeju Combined Cycle Unit 3 is noteworthy because it could affect not only an individual project but also future electricity supply and demand. In particular, there is growing concern about a potential supply gap if the commissioning of new facilities is delayed, given that the end of life for many aging power plants is concentrated around 2030.


Korea Midland Power is also reviewing countermeasures in light of these risks. The board agenda included plans to continue operating (extend the lifespan of) or replace facilities at major power plants in Boryeong, Incheon, and Jeju as their operating lives expire. Some facilities are also under consideration for conversion to heat supply units or for hydrogen co-firing power generation.



The power generation industry is paying close attention to the possibility that this issue could recur throughout future power projects. An industry official said, "Since the global power equipment supply crunch is unlikely to be resolved in the short term, it is necessary to formulate facility construction plans more conservatively, based on the premise of equipment availability."


This content was produced with the assistance of AI translation services.