The Intensifying Large Turbine Battle ... Korean Offshore Wind Power Strategy Put to the Test [The Road to Wind Power Independence] ⑤ (End)
Successful Development of 10 MW Turbines, Now Entering Commercialization
Overseas Leaders at 15-20 MW... 70% Technological Self-Sufficiency
"Large-Scale Mass Production Needed to Lower Costs and Boost Competitiveness"
"It has been over a decade since offshore wind power was declared a national project, and although several major companies formed business consortiums only to withdraw, Doosan Heavy Industries & Construction (now Doosan Enerbility) never gave up, which is why we have reached the current level. I would like to express my special gratitude."
This was a statement by former President Moon Jae-in in July 2020, when he was briefed on offshore wind power development plans during his visit to the Wind Power Core Technology Center in Buan County, North Jeolla Province.
In 2010, the Lee Myung-bak administration announced the 'Renewable Energy Industry Development Strategy,' expressing its ambition to nurture solar power as the 'second semiconductor industry' and wind power as the 'second shipbuilding industry.' Around this time, major companies such as Samsung Heavy Industries, Hyundai Heavy Industries, and Daewoo Shipbuilding & Marine Engineering entered the wind power business, but all eventually withdrew.
However, Doosan Enerbility persisted and continued its business until the end. On that day, Doosan introduced its self-developed 5.5 MW wind turbine to President Moon. This product has been installed in the 100 MW Jeju Hallim Offshore Wind Power project, which was completed in December last year.
Six years ago, former President Moon remarked, "We have always had an advantage in substructures, so we are already at the world's top level in that area. If we can fully localize turbine technology, we can also reach the top tier globally." Since then, Doosan Enerbility has successfully developed 8 MW and even 10 MW wind turbines, which are now on the verge of commercialization. So, to what extent has Korea's wind turbine technology advanced?
Korean Wind Power Technology at 70% of Overseas Level
According to the '2025 Energy Technology and Industrial Ecosystem Analysis' published by the Korea Institute of Energy Technology Evaluation and Planning at the end of last year, Korea's offshore wind power system's technological self-sufficiency stands at about 70% compared to leading countries. While Korea has just completed its 10 MW demonstration, global leaders such as Vestas (Denmark), Siemens Gamesa (Germany), and Goldwind (China) have already commercialized 15-16 MW turbines. German and Chinese companies have either demonstrated or are developing wind turbines with a capacity of 20 MW or more.
Specifically, the domestic wind turbine system design and assembly level is at 75%, blades at 70%, gearboxes at 50%, yaw and pitch drives at 70%, yaw and pitch bearings at 70%, and generators at 65%. Towers and fixed substructures are both rated at 90%, which is on par with leading companies. As was the case six years ago, rapidly catching up in turbine technology remains a key challenge.
Under the Lee Jaemyung administration, there has been renewed focus on expanding renewable energy, once again drawing attention to offshore wind. The government plans to supply 100 GW of renewable energy by 2030, with offshore wind accounting for 3 GW of this goal. While many generation business permits have been issued so far, progress remains slow due to delays in project execution.
The government is trying to accelerate offshore wind power deployment while also aiming to reduce costs. At the same time, it faces the difficult task of nurturing the domestic supply chain.
Some in the wind power industry argue that "importing cost-effective Chinese equipment or large 15 MW class European turbines is necessary to lower investment costs." This view is particularly prevalent among overseas developers and financial institutions that prioritize economic feasibility.
For example, to develop a 300 MW offshore wind farm, installing 30 domestically produced 10 MW turbines would be required, while only 20 units of 15 MW turbines would suffice. Reducing the number of installations lowers investment costs and the price of renewable energy. Some argue that importing foreign turbines while using domestically produced towers and substructures, where Korea is competitive, would be sufficient.
However, in that case, the hard-won domestic turbine ecosystem could collapse. Ultimately, there are concerns that the supply chain could become dependent on foreign companies, as seen in Japan and Taiwan.
"A Standard Korean Offshore Wind Power Model Must Be Established"
Experts point out that, for energy security and domestic industry development, it is important to first establish a robust ecosystem for domestically produced 10 MW turbines. Through experience in mass production and large-scale installation, a standardized model can be created to significantly lower installation costs. This approach can both reduce renewable energy prices and foster the domestic supply chain.
Kang Geumseok, Wind Power PD at the Korea Institute of Energy Technology Evaluation and Planning, said, "For wind power to grow explosively in any country, a domestic supply chain is essential," and added, "Domestic companies need to gain experience with gigawatt (GW)-scale mass production." Kang also emphasized, "Whether it is 10 MW or 15 MW, the current technology needs to be rapidly deployed to lower costs and build technical capacity." He explained that only then can Korea develop the capability to produce 20 MW wind turbines in the future.
Careful assessment is also needed as to whether installing large 15 MW class foreign turbines will actually lower costs.
Professor Lee Sangil of the Department of Wind Power Engineering at Kunsan National University pointed out, "Investment costs should not be evaluated solely based on the number of installations," and added, "It is necessary to comprehensively consider operating and maintenance costs, as well as response capabilities in the event of failures, over the entire 20-year operation period."
Professor Lee further stated, "The significance of renewable energy lies in contributing to energy security by not importing fuel, but if equipment is imported, that significance is lost. Only by using domestically produced equipment can we actually substitute for fuel imports."
Some experts also stress that when introducing large foreign turbines, 'domestic production (made in Korea)' must be a prerequisite.
Professor Kim Beomsu of the Department of Wind Power Engineering at Jeju National University commented, "Simply importing and installing turbines from Europe or China does not help the domestic industry at all. It is necessary to induce foreign turbine manufacturers to form joint ventures with Korean companies for local production and technology transfer, as exemplified by the Doosan Enerbility-Siemens Gamesa collaboration model."
Currently, Doosan Enerbility is building a major assembly plant for Siemens Gamesa turbines in Changwon, conditional on technology transfer. In contrast, Vestas of Denmark announced plans to invest KRW 300 billion to build a turbine plant in Mokpo, but there has been no progress so far.
"Failure to Develop 20 MW Turbines in Time Could Lead to Obsolescence"
Experts recommend not only deploying the previously developed 10 MW class turbines but also rapidly following the trend toward larger turbines.
The government is currently pursuing the development of 20 MW class wind turbines as a national project. Government-funded research institutes are participating in basic design work, with the goal of producing a prototype in the early 2030s.
Professor Kim Beomseok of Jeju National University stated, "If domestic companies can timely develop, supply, and foster 20 MW turbines, they will be able to compete with European and Chinese companies in the market. If they fail, they could become completely obsolete."
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Companies point out that developing 20 MW class wind turbines requires massive investment, so incentives are needed. A Doosan Enerbility official said, "To manufacture 20 MW class wind turbines, a new plant must be built, and the development cost alone is estimated at a minimum of KRW 500 billion to KRW 600 billion. From a corporate perspective, it is difficult to make investment decisions unless there is a clear link to actual commercialization."