Active Use of 'One-Point Increase' for Specific Construction Materials

Public Sector Virtual Assets Worth 78.3 Billion Won Undergo 'Security Overhaul'… Mandatory Split Storage Implemented

The government is switching the public procurement market to an "emergency management system" in response to soaring raw material prices and supply instability caused by the prolonged Middle East war. The government will temporarily ease the restriction period for contract price adjustments due to price fluctuations, and will introduce a "one-point increase" measure to raise the price of specific construction materials separately if their prices surge.


Construction costs may be increased even before 90 days… Private sector left unprotected


Construction site of Yongin Semiconductor Cluster. The Asia Business Daily DB.

Construction site of Yongin Semiconductor Cluster. The Asia Business Daily DB.

View original image

On April 10, the government held an Emergency Economic Headquarters Meeting and a Meeting of Economy-Related Ministers, and announced "Support Measures for Public Contracts Related to the Middle East War" in cooperation with relevant ministries. The key point is to use all possible exception clauses and guidelines to alleviate the cost burden on companies.


For example, under the current State Contracts Act, contract price adjustments to reflect price changes are only allowed after 90 days from the signing of the contract. However, the government will apply an exception clause that allows adjustments within 90 days in cases of force majeure or dramatic raw material price increases. In particular, if the price of a specific material surges by more than 15% compared to the bid date or the most recent adjustment date, each ministry is instructed to actively use the "single-item price adjustment system," which allows the immediate increase of the cost for that material even if the overall inflation rate does not meet the criteria for adjustment.


Additionally, if raw material supply disruptions delay delivery, the government will exempt companies from liquidated damages and extend delivery deadlines. To ease liquidity burdens, companies will be allowed to submit a "payment letter" instead of a bid deposit.


The speed of reflecting market prices will also be significantly increased. After the Public Procurement Service’s regular construction material price survey is released on April 20, the survey cycle will be greatly shortened from the current semi-annual schedule. For "special materials" with highly volatile prices, such as oil or naphtha, prices will be monitored weekly. For about 1,500 "key materials" like steel, prices will be monitored monthly, and if prices rise by more than 5% compared to the previous survey, the increase will be immediately reflected in construction costs. The government also plans to announce signs of "price increase due to inflation (ES)" every month on the Public Procurement Service website so that companies can apply for construction cost adjustments in a timely manner.


However, these measures are limited to the public sector and do not apply to private construction sites, which account for around 180 trillion won annually. A government official explained, "The State Contracts Act only applies to public sector projects. The private sector is governed by the principle of private autonomy, so there are limitations. I understand that the Ministry of Land, Infrastructure and Transport is preparing separate measures."


Frequent incidents with public sector virtual assets… Mandatory splitting of 'mnemonic code' storage


On the same day, the government finalized its "Plan to Improve the Public Sector's Virtual Asset Holding and Management System," which covers virtual assets seized or held by public agencies such as the prosecution or police during investigations or tax collection. Currently, central and local governments and public agencies combined hold about 78.3 billion won worth of virtual assets.


According to the plan, to prevent the exposure of "recovery phrases (mnemonic codes)"—the main cause of recent leaks—access rights such as private keys must now be managed in split form by at least two responsible persons. All virtual assets must be stored in "cold wallets," which are isolated from the internet, and physical security measures such as safes and CCTV must be installed. If an incident occurs due to a violation of these guidelines, those responsible will be strictly disciplined.



A government official stated, "Previously, virtual assets were managed similarly to general seized items, but with these guidelines, we have established a standard system suited to the technical characteristics of virtual assets. If an incident occurs due to a violation of the guidelines, those responsible will face strict disciplinary action, ranging from warnings to dismissal."


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.