First Phase of 40MW Approved
Construction Set for 2027, Operations Targeted for 2028

The 1.38 trillion won investment project for the "Hamyang AI Data Center" completed its final permits and approvals as of April 9, 2026, officially entering the full-scale implementation phase.


This approved project represents the first phase of the overall plan, with a capacity of 40MW. It will be constructed on a 42,738㎡ (approximately 12,928 pyeong) site within the Hucheon General Industrial Complex, with a total floor area of 30,807㎡ (about 9,319 pyeong). The main facilities will comprise two five-story computer buildings and one three-story operations building. Heerim Architects & Planners, a leading architectural design firm in Korea, is in charge of the comprehensive design, bringing professional expertise to the project.


Aerial View of Hamyang AI Data Center

Aerial View of Hamyang AI Data Center

View original image

The "Hamyang AI Data Center" is also making smooth progress in securing foundational infrastructure. After signing a power supply agreement with Korea Electric Power Corporation in December 2024, the project passed a 100MW power grid impact assessment in February of this year, establishing a stable power network.


In particular, significant effort has been devoted to addressing environmental and safety concerns. The Hucheon General Industrial Complex, where the center will be located, is situated in a basin over 1km away from nearby villages, minimizing concerns about electromagnetic waves, noise, and the urban heat island effect. In addition, to protect water resources, the center is planned to use an air-cooled system to dissipate heat, rather than methods that require large amounts of water.


The investor, Orid Korea Co., Ltd., is currently finalizing funding and securing client companies. Following further preparations, the company plans to begin construction in 2027 and commence full-scale operations in 2028.


Meanwhile, prior to the permit approval, Hamyang County held a project briefing at the Hucheon-myeon village head meeting on April 7, 2026. During this event, the county explained in detail the location advantages, anticipated economic benefits, and environmental safety of the data center, seeking the understanding of local residents.



An official from Hamyang County stated, "We will continue to arrange opportunities for communication by holding additional briefings for residents together with investors and partner companies. Not only will we transparently share the progress of the project with the community, but we will also provide full administrative support to ensure the construction of the data center proceeds smoothly and becomes a new driver for revitalizing the local economy."


This content was produced with the assistance of AI translation services.