Gapyeong County to Complete Major Work at 303 Heavily Damaged Sites Before Rainy Season

Gapyeong County in Gyeonggi Province is accelerating the restoration of public facilities to ensure early recovery of areas damaged by last year’s heavy rainfall.

Gapyeong County held the 4th countermeasure meeting for the '2025 Early Promotion Task Force (TF) Team for Flood Damage Recovery Projects' on the 31st at the Disaster Safety Situation Room, chaired by Vice County Governor Mi-sung Kim, with 22 department heads related to disaster recovery projects attending. Provided by Gapyeong County

Gapyeong County held the 4th countermeasure meeting for the '2025 Early Promotion Task Force (TF) Team for Flood Damage Recovery Projects' on the 31st at the Disaster Safety Situation Room, chaired by Vice County Governor Mi-sung Kim, with 22 department heads related to disaster recovery projects attending. Provided by Gapyeong County

View original image

On March 31, Gapyeong County held the 4th countermeasure meeting of the "2025 Early Promotion Task Force (TF) Team for Flood Damage Disaster Recovery Projects" at the Disaster Safety Situation Room, chaired by Deputy County Governor Mi-sung Kim, with 22 department heads related to disaster recovery projects in attendance.


Since the severe damage caused by torrential rain in July of last year, the county has been making all-out efforts for disaster recovery by forming an early promotion TF team led by Deputy County Governor Mi-sung Kim. At the meeting, the team closely examined the results of construction orders, future completion plans, and the reasons for delays in projects. In particular, for 303 disaster recovery sites—excluding six river improvement and restoration projects—they decided to complete major processes before this year's rainy season and to monitor the progress on a weekly basis.


For the six river improvement and restoration projects, including the heavily damaged Mile Stream, the county plans to reinforce personnel for land compensation and shorten administrative procedures to complete the projects by December 2027. In addition, for the Homyeongsan entrance pedestrian bridge in Cheongpyeong-myeon, the construction order for design was delayed due to complaints about converting it to a vehicle bridge. However, the county has decided to proceed with the demolition of the pedestrian bridge and to begin the design service order process.



Deputy County Governor Mi-sung Kim stated, "We are prioritizing minimizing inconvenience for residents and ensuring complete disaster recovery," and added, "For projects experiencing slow progress, we will continue regular inspections and do our utmost to achieve early completion."


This content was produced with the assistance of AI translation services.