43,000 Units through Land Development Including Daejang New Town
104,000 Units via Housing Redevelopment Projects such as Jung-dong First-Phase New Town
Administrative Permit Processing Time to Be Reduced by Over 30%

Bucheon City in Gyeonggi Province will supply approximately 147,000 housing units by 2035 through land development projects such as Daejang New Town and various housing redevelopment initiatives.


On March 26, the city announced its 'Bucheon-Style Residential Innovation Project' roadmap, outlining the basic direction and detailed implementation plans for housing supply. The city plans to supply 93,000 units by 2030 and 147,000 units by 2035, rolling them out in phases across 172 locations throughout Bucheon to ensure stable medium- and long-term housing supply.


By region, Wonmi-gu accounts for the largest portion with 80,000 units. Ojeong-gu will lead the initial move-in process by supplying about 43,000 units through large-scale land development projects, including the development of Daejang New Town, from this year through 2028. Sosa-gu plans to supply around 24,000 units, mainly through the reconstruction of Goean-dong and Sosabon-dong and small-scale redevelopment projects.


Among the large-scale new land developments, public sales for about 1,500 units in Daejang and Yeokgok New Towns will begin this year, with private sector sales starting in earnest from next year. The city intends to strategically allocate public and private housing supplies to establish a self-sustaining city foundation that integrates advanced industries and culture, thereby revitalizing the local economy.


Overview of Bucheon City Housing Supply Policy. Provided by Bucheon City

Overview of Bucheon City Housing Supply Policy. Provided by Bucheon City

View original image

Additionally, the city will provide about 104,000 units, representing around 70% of the total supply, through 'housing redevelopment projects' to revitalize existing aging residential areas.


First, Jung-dong's first-phase new town will be reorganized into a future-oriented city by integrating 48 complexes—currently home to 40,000 households—into 18 unified redevelopment zones, ultimately expanding to a total of 64,000 units. The city aims to start construction on 54,000 units, which is 85% of the planned households, by 2035. The plan involves large-scale, integrated redevelopment and the reallocation of essential social infrastructure (SOC) to boost urban efficiency, while also creating eco-friendly urban spaces centered on walkability, green spaces, and culture.


Furthermore, for Eunha Village and Bandal Village, which have already been designated as pilot districts, the process of proposing redevelopment zone designation and obtaining resident consent is currently underway. The city plans to complete the master plan by May and, starting in June, will use specific guidelines as instructions for redevelopment planning.


For the old downtown area, the policy direction will shift from small-scale redevelopment to comprehensive, citywide projects, aiming to supply about 50,000 units by 2035 and fully restore urban functions.


The 'Mini New Town Project' in the areas of Simgokbon-dong and Wonmi-dong will be promoted with the goal of district designation this year and groundbreaking in 2031, leveraging incentives such as relaxed floor area ratios and changes in land use classification. The 'Bucheon-Style Station Area Redevelopment Project' is gaining momentum with the establishment of a redevelopment plan for Jung-dong Station and preparations for Sosa Station, and new target sites will be selected this year.


The Bucheon-Wonmi Urban Complex Project and major redevelopment and reconstruction projects will also be pursued in parallel. The city plans to expand resident-led redevelopment approaches based on citizen proposals, and enhance project viability through measures such as land use upgrades, floor area ratio incentives, and easing of public contribution requirements. In addition, 'Reconstruction Fast Track' and 'Joint Review' systems will be introduced to accelerate project timelines.


To enhance the execution of housing supply projects, the city will reduce the processing period for administrative permits, such as building approvals, by more than 30% compared to current durations. The goal is to shorten the average 114-day permitting period under the Urban Redevelopment Act to 79 days. To achieve this, the city will implement shortening measures in the first half of the year and, in the second half, establish computerized systems such as an integrated permit consultation search platform.



Jang Hwansik, Director of Housing, stated, "This housing innovation project will serve as a turning point for fundamentally transforming the city's structure, going beyond simply expanding housing supply," adding, "We will ensure tangible residential stability for citizens through swift administrative support and regulatory improvements."