Government Encourages Work Stoppage Rights, but Construction Industry Says "Main Contractors Bear Full Cost Burden"
Four Major Construction Firms Used Work Stoppage Rights Over 270,000 Times Last Year
Incentives and Compensation Systems Encourage Use
DL E&C Reports 100,000 Cases, While Small and Mid-Sized Firms Log Only 280
“Cost Burden Limits Us”...Main Contractors Shoulder Delays and Expenses
Last year, the number of work stoppage rights exercised by the four major construction companies exceeded 270,000 cases. In line with the government’s policy focus on preventing serious industrial accidents, it is evaluated that the right to stop work has become established at large construction sites. However, since the main contractors are shouldering the cost burden resulting from work stoppages, there are growing calls for urgent improvements to the system to facilitate the spread of work stoppage rights to small and medium-sized construction companies.
According to the industry on the 25th, the four major construction companies—Samsung C&T, Hyundai Engineering & Construction, GS Engineering & Construction, and DL E&C—exercised work stoppage rights 273,240 times last year. This represents an increase of approximately 14% (35,135 cases) over two years compared to 238,105 cases in 2023. The work stoppage right is a right guaranteed by the Industrial Safety and Health Act, allowing workers to halt work when there is an imminent risk of an industrial accident.
◆Large Companies Compensate Subcontractors’ Losses...Incentive Systems Introduced
Major construction firms are actively encouraging workers to exercise their right to stop work by establishing reporting systems and awarding incentives. Samsung C&T recorded 167,582 cases of work stoppage right exercised last year—the highest in the industry. The accumulated number of cases over the past three years has exceeded 630,000. DL E&C reported a cumulative total of 103,431 cases between 2023 and 2025, and Hyundai Engineering & Construction saw its number of cases surge from 18,337 in 2023 to 46,500 last year. GS Engineering & Construction reported a three-year cumulative total of 10,589 cases. The increase has been significantly influenced by policies awarding workers for exercising their right to stop work, and by some companies operating systems that compensate subcontractors for losses caused by construction delays and additional manpower deployment.
The government’s emphasis on strengthening safety management is a key factor behind large construction companies’ encouragement of work stoppage rights. On March 19, Minister of Land, Infrastructure and Transport Kim Yoonduk presented plaques of appreciation to the four companies (Samsung C&T, Hyundai Engineering & Construction, DL E&C, GS Engineering & Construction) at a meeting with construction company CEOs, praising their achievements in promoting the right to stop work. The ruling party is currently pursuing amendments to the Industrial Safety and Health Act to expand eligibility for exercising the right to stop work, and to strengthen penalties for employers who unfairly penalize employees for using this right.
◆Small and Medium-Sized Companies Heavily Dependent on Public Projects...Shouldering the Full Cost Burden
While the right to stop work is being exercised mainly by large construction companies, it has not yet spread across the construction industry as a whole. Because the main contractor must bear the costs of work delays and additional construction expenses resulting from stoppages, it is not easy for small and medium-sized firms to make use of the system. The high proportion of civil engineering or small-scale maintenance projects also means that profit margins at these sites tend to be low. For example, one mid-sized construction company that requested anonymity exercised the right to stop work only 245 times in 2023 and 280 times in 2024. Another mid-sized company recorded only about 500 cases in total over three years.
An on-site safety manager at a mid-sized construction company said, “We have no choice but to take a conservative approach when it comes to using the right to stop work, given the risk of construction delays, rising costs, and quality degradation.”
The heavy reliance on public sector projects is also cited as a factor increasing the burden. Small and medium-sized construction companies depend heavily on government-ordered projects for their contracts, making it difficult to ask the public sector client to shoulder the losses. The Industrial Safety and Health Act does not specify who is responsible for the costs incurred when exercising the right to stop work. As a result, the party responsible for delays is typically required to bear the losses. A representative of a mid-sized construction company said, “In the case of public works, the contractor usually ends up taking responsibility for delays.”
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Industry insiders argue that to ensure the right to stop work functions effectively, improvements are needed to the cost-sharing system. One industry source said, “For government-ordered projects, there needs to be a clear set of guidelines specifying incentives for encouraging the right to stop work, as well as criteria for cost compensation between the main contractor and the client. Only if concerns about responsibility for delays and cost burdens are resolved will the system be actively used on-site.”