'Bujeon-Masan Double-Track Railway Delayed for 5 Years, Timely Opening Urged ... "Professional Mediation Essential"'
Jung Hoon Choi and Mina Kim, members of the Changwon Special City Council in Gyeongnam Province, have called for the timely opening of the 'Bujeon~Masan double-track railway' through mediation by a professional institution.
On March 23, the two council members held a press conference at the city hall press center, stating, "The Bujeon~Masan double-track railway project is a key axis of the national trunk railway network, connecting the Gyeongjeon Line, Gyeongbu Line, and even the Donghae Nambu Line. However, the opening has been delayed during successive government transitions. Local residents and the regional economy are bearing the brunt of these delays."
They further pointed out, "During the excavation of the evacuation connection passage, a major ground subsidence accident occurred, delaying the construction. Although the restoration work has now been completed, the Ministry of Land, Infrastructure and Transport and the project operator continue to dispute responsibility over design changes and other issues, resulting in further delays to the opening."
They also criticized, "Due to the project delays, the plan to establish a 30-minute living sphere for Busan, Ulsan, and Gyeongnam has been disrupted. Increased logistics transport costs have reduced operational efficiency for businesses, while weakened transportation accessibility has led to a decline in tourism and commercial activity, causing serious social and economic side effects."
Junghoon Choi and Mina Kim, members of the Changwon Specialized City Council in Gyeongnam Province, are holding a press conference urging the timely opening of the Dupjeon-Masan double-track railway through mediation by a specialized agency. Photo by Seyoung Lee
View original imageThey emphasized, "Among local residents, there is growing cynicism that if this project were in the Seoul metropolitan area, it would have opened several times already. This sense of structural deprivation and anger over non-capital regions always being pushed back is deepening."
They continued, "In the Seoul metropolitan area, major rail lines such as the GTX-A Dongtan~Suseo South Line and the Unjeong Jungang~Seoul Station North Line have opened smoothly, connecting Paju in Gyeonggi Province to Seoul Station in just over 20 minutes. In contrast, 8 million residents of Busan, Ulsan, and Gyeongnam are left without a proper metropolitan railway network."
The two council members demanded, "The Ministry of Land, Infrastructure and Transport and the project operator must no longer evade their administrative and technical responsibilities. They must immediately present a clear and actionable roadmap for the timely opening."
They particularly stressed, "A binding arbitration decision by a credible institution is essential regarding the construction of the evacuation connection passage, which is the main point of contention. Only objective mediation and judgment by an institution with expertise in railway safety, civil engineering, and disaster prevention can resolve the dispute and bring the project back on track."
They added, "To prevent further waste of time and social costs, mediation by a professional institution such as the Korean Commercial Arbitration Board is absolutely necessary."
Additionally, they stated, "While Gyeongnam Province has proposed partially opening completed sections first, full-scale opening must happen as soon as possible in order to fully realize the purpose of the project, even if partial opening is pursued first."
The two council members stated, "This is clearly an issue of government policy priority and execution will. For the development of the southeastern region and the balanced development of the nation, this problem must not be neglected. Any further neglect of the opening is tantamount to disregarding the daily lives of local residents and undermining national trust and competitiveness. Authorities must approach this issue responsibly and solve the problem."
The Bujeon~Masan double-track railway is a rail line that connects about 51 kilometers across nine sections, from Bujeon Station in Busan through Sinwol Station in Gimhae, Gyeongnam Province, to Masan Station in Changwon City.
Construction began in April 2014 and was scheduled for completion in 2020, but the project was halted just before opening when the lower Nakdong River tunnel collapsed.
It took more than five years just to restore the accident section, and with 99% of the construction completed, the government and the project operator have failed to reach an agreement over issues such as the addition of evacuation connection passages, causing the opening to be delayed for five consecutive years.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Ultimately, through a revision of the implementation plan for the private investment facility project announced in December last year, the government extended the construction period by another year, postponing the opening date, which had been stated as June 2026 during the parliamentary audit, to the end of the year.