[Exclusive] "We Will Follow the President," But Only 6% of Staff Assigned... Is Renewable Energy Expansion Possible?
Total Workforce of Five Companies: 13,440
Only 792 Engaged in Renewable Energy Roles
"Urgent Need to Expand Workforce Transition at Power Companies"
Offshore Wind Power in Yaksu, Yeonggwang, Jeollanam-do. The Yaksu Offshore Wind Power project has a capacity of 4.3 MW and is located about 2.5 km off the coast of Baeksu-eup, Yeonggwang County. It is a pilot project implemented by the Jeonnam Development Corporation, marking the first time a local public enterprise has undertaken such a project. Photo by Kang Jin-hyung
View original imageIt has been found that employees responsible for renewable energy account for less than 6% of the total workforce across Korea’s five major state-run power generation companies. Although all these companies are publicly pledging to expand renewable energy in anticipation of the closure of coal-fired power plants by 2040, there is a notable shortage of staff to actually drive these initiatives. This highlights the urgent need for a substantial restructuring of the workforce in line with the country’s energy transition.
According to data obtained on March 23 by The Asia Business Daily from Assemblywoman Park Ji-hye of the Democratic Party of Korea (representing Uijeongbu, Gyeonggi Province), as of February, there were a total of 792 employees engaged in renewable energy-related work at the five major power generation companies (Korea East-West Power, Korea Western Power, Korea South-East Power, Korea Southern Power, and Korea Midland Power). This represents only 5.9% of the total workforce of 13,440 employees.
By company, Korea South-East Power had the highest proportion, with 285 out of 2,816 employees (10.1%) working in renewable energy-related roles. Korea East-West Power followed with 6.6%, Korea Midland Power with 6.0%, Korea Southern Power with 3.9%, and Korea Western Power had the lowest at 2.9%.
The Lee Jae-myung administration has set an ambitious target to increase renewable energy capacity from the current 35GW to 100GW by 2030. The Ministry of Climate, Energy, and Environment plans to significantly expand public-led projects, including solar power installations in industrial complexes and rooftop solar, as well as onshore and offshore wind power projects, to achieve this goal.
The power generation companies have also declared, “We will actively participate in the government’s policy,” announcing organizational reforms and bold new targets. However, based on the current staffing levels, there are doubts about whether these companies can actually take the lead in developing renewable energy. Within the energy industry, there have been frequent criticisms that these companies have only lent their names to renewable energy projects, lacking the actual operational capabilities required.
Assemblywoman Park Ji-hye stated, “Despite the government’s targets for expanding renewable energy, the five power generation companies are inadequately prepared in terms of staffing on the ground,” and urged, “It is urgent to actively reassign personnel for the renewable energy transition and to expand the development of renewable energy projects, so that meaningful transformation measures are implemented by these companies.”
In Words, “Transforming into Renewable Energy Companies,” But the Reality Is...
The government’s policy is to actively utilize public institutions in order to expand renewable energy capacity to 100 gigawatts (GW) by 2030. For example, the Ministry of Climate, Energy, and Environment is encouraging public institutions to participate in solar projects using idle land or factory rooftops in industrial complexes. It is expected that rooftop solar installations in factories alone could expand renewable energy capacity by up to 20GW. The government has also opened a separate public-led offshore wind power bidding market, enabling public institutions to participate.
The government plans to abolish the Renewable Portfolio Standard (RPS) so that state-run power generation companies are no longer limited to simply purchasing Renewable Energy Certificates (RECs), but are instead encouraged to actively install and supply renewable energy.
As power generation companies must completely phase out coal-fired power plants by 2040, they have expressed their intention to transform into renewable energy companies by reorganizing their structures and announcing challenging targets. However, given the current staffing levels, there are concerns about whether they can actually fulfill these expanded roles.
Korea Western Power reorganized its structure at the end of last year to establish the Renewable Energy Business Division and the New and Renewable Energy Operations Center. It also announced mid- to long-term plans to increase renewable energy capacity to 3.9GW by 2030 and 13.5GW by 2040. However, of its total 2,704 employees, only 81 are engaged in renewable energy roles. Among the 32 staff in the Renewable Energy Business Division, only 8 work in the wind power unit and 6 in the solar power unit.
Regarding this, Korea Western Power stated, “Including staff responsible for the management and safety of renewable energy facilities at branch offices, the actual number of employees engaged in renewable energy is 127,” adding, “We plan to actively expand the workforce in this sector through future organizational streamlining and job reassignment.”
Korea Western Power’s Taean Thermal Power Plant ceased operation of its Unit 1 at the end of last year, and plans to sequentially shut down up to Unit 8 by 2037. The company explained, “We are making active efforts to expand renewable energy by reassigning staff from decommissioned thermal power plants to renewable energy, and we are supporting job transition training for partner company employees through consultations to ensure employment stability.”
Korea Southern Power, which had 906MW of renewable energy capacity as of the end of last year, has set a goal to increase this to 3,714MW—four times the current level—by 2030. The company also established a Renewable Energy Headquarters through organizational reform at the end of last year. However, there are only 105 employees in renewable energy roles out of a total workforce of 2,633.
Korea Southern Power will begin by shutting down Hadong Unit 1 coal-fired power plant in June this year and will sequentially close up to Hadong Unit 6 by 2031. These plants will be replaced by combined cycle power plants using liquefied natural gas (LNG), so the reallocation of staff is expected to focus more on combined cycle operations than on renewable energy. Last year, the company conducted training for 70 employees on six occasions, with most of the training focused on maintenance and operation of combined cycle plants.
Coal Plants Closing One After Another... Workforce Transition Remains a Challenge
Korea Midland Power stated that, out of a total of 2,730 employees, 153 are engaged in renewable energy work. The company reassigned 25 employees previously working at headquarters and major thermal power plants (Boryeong Headquarters, Shin-Boryeong Headquarters, and Jeju Headquarters) to renewable energy-related divisions.
Korea Midland Power plans to shut down its Boryeong Units 5 and 6 thermal power plants between this year and next. The company said it will conduct “Capacity Up for Energy Transition” training this year for 250 employees, including those working at these sites. Currently, Korea Midland Power has 1,725MW of renewable energy capacity and aims to raise the share of renewables to 30% by 2035.
Korea East-West Power has 168 employees working in renewable energy roles out of a total workforce of 2,557. The company aims to double its renewable energy capacity from 1,440MW at the end of 2025 to 2,789MW by 2030. However, in the Renewable Energy Division, which oversees these efforts, there are only 4 employees each responsible for solar, onshore wind, and offshore wind projects.
Korea East-West Power stated, “As the timeline for coal plant closures (September 2029) has not yet arrived, there has not been a need to reassign existing facility staff. We plan to reallocate personnel in line with the generation mix as the closure dates approach.”
Korea South-East Power, including 206 workers stationed at power plants, has 285 employees engaged in renewable energy work, accounting for 10.1% of its total workforce of 2,816. The company plans to expand its renewable energy capacity from the current 1,362MW to 9,935MW, or 40% of its total capacity, by 2040.
Korea South-East Power stated, “Due to the closure of coal-fired plants, the total number of employees is expected to be reduced by about 1,800 by 2040. We plan to reassign 1,100 employees to natural gas cogeneration projects, 400 to renewable energy development and operations, and 300 to carbon-free power projects utilizing idle sites.”
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Meanwhile, Korea Hydro & Nuclear Power has 161 employees in renewable energy-related teams such as the Renewable Energy Division, Hydrogen Fusion Division, and Nuclear Hydrogen Fusion Center. This represents only 1.4% of its total workforce of 11,360. Korea Electric Power Corporation, which is not permitted under the Electricity Business Act to directly operate power plants, is responsible for domestic and overseas renewable energy project development through its Offshore Wind Power Business Division and ESS & Renewable Business Unit, which have 41 and 7 employees, respectively.
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.