Kori Unit 2 to Restart as Early as Late March
Spotlighted Amid Middle East Energy Security Crisis
Significance as First Application of Accident Management Plan
Facility Upgrades Include Mobile Generator and Pump Trucks
Measures in Place for Power Supply Loss and Cooling System Failures

View of Kori Units 1 and 2. Nuclear Safety and Security Commission

View of Kori Units 1 and 2. Nuclear Safety and Security Commission

View original image

On March 18, even as spring rain fell, the Korea Hydro & Nuclear Power Gori Nuclear Power Headquarters was bustling with activity. This was because Choi Wonho, Chairman of the Nuclear Safety and Security Commission, and Kim Hoechun, the newly appointed President of Korea Hydro & Nuclear Power, both visited the site on the same day, just a few hours apart, ahead of the restart of Kori Unit 2.


"We will complete all preparations by the 25th so that we can restart operations at the end of March or in early April."


Choi Dongcheol, Director of the No. 1 Power Plant at Gori Nuclear Power Headquarters, reported the current status to Chairman Choi during his visit. If everything proceeds as planned, Kori Unit 2, which suspended operations when its design life expired on April 8, 2023, will resume operations after exactly three years.


The Nuclear Safety and Security Commission granted approval for the continued operation of Kori Unit 2 in November of last year. For a nuclear power plant to continue operating, it must pass the Periodic Safety Review (PSR) and Operating License Amendment reviews conducted by the Korea Institute of Nuclear Safety (KINS).


Prior to this, in October, the accident management plan was also approved. The accident management plan outlines measures to prevent incidents similar to the Fukushima nuclear accident from recurring, even during disasters such as tsunamis. Kim Jihun, Project Manager for accident management plan regulation at KINS, explained, "Kori Unit 2 is the first to fully equip its facilities according to the accident management plan."


The Fukushima nuclear accident in 2011 occurred when all power sources, including emergency generators, were lost due to flooding from a tsunami, causing the coolant pumps to stop and the reactor core to melt down. Hydrogen gas generated inside the reactor then exploded, leading to a major disaster. In response, the accident management plan was established.

Chairman Choi Wonho of the Nuclear Safety and Security Commission is listening to an explanation about the preparation status for the restart of Gori Unit 2 from a Korea Hydro & Nuclear Power official on March 18, 2026. Nuclear Safety and Security Commission

Chairman Choi Wonho of the Nuclear Safety and Security Commission is listening to an explanation about the preparation status for the restart of Gori Unit 2 from a Korea Hydro & Nuclear Power official on March 18, 2026. Nuclear Safety and Security Commission

View original image

Following the approval for continued operation of Kori Unit 2, Korea Hydro & Nuclear Power invested approximately 170 billion won to upgrade its facilities in order to implement the requirements detailed in the PSR and accident management plan approved by the Nuclear Safety and Security Commission.


In fact, during the visit, the yard at Gori Nuclear Power Headquarters was lined with equipment such as mobile pump trucks, multi-articulated cranes, and mobile generator vehicles, all ready to be deployed immediately in the event of a disaster. These pieces of equipment are used if power supply within the plant is disrupted or if problems occur in the cooling water system.


Project Manager Kim Jihun explained, "These devices are usually stored at higher elevations than the plant site and are moved into place if a natural disaster temporarily renders the fixed safety equipment inside the containment building unusable."

A newly installed 1MW portable power generator truck for the restart of Gori Nuclear Power Plant Unit 2. It is usually stored within a 2.45M containment wall. Korea Hydro & Nuclear Power

A newly installed 1MW portable power generator truck for the restart of Gori Nuclear Power Plant Unit 2. It is usually stored within a 2.45M containment wall. Korea Hydro & Nuclear Power

View original image

The mobile generator vehicles are intended to supply power to reactor safety systems during emergencies, and two types have been fully prepared: 1 megawatt (MW) and 3.2 MW. The 1 MW mobile generator vehicle is usually stored inside a 2.45-meter-high flood barrier wall. Korea Hydro & Nuclear Power explained that this provides a safety margin of 0.45 meters above the maximum flood level of 2.0 meters. This equipment is deployed within eight hours in the event of a total loss of power at the plant.


If a blackout persists for more than 72 hours, the larger 3.2 MW mobile generator vehicle will be used to supply power.


High-pressure and low-pressure mobile pump trucks, as well as high-capacity mobile generator vehicles, are designed to supply emergency cooling water from outside the plant to prevent core meltdown in case the internal power supply is lost and cooling systems fail. Depending on the pressure inside the reactor, a high-pressure pump truck is used first, followed by a low-pressure pump truck as the pressure drops.


High-pressure mobile pump truck newly installed and operating method for the restart of Kori Nuclear Power Plant Unit 2. Korea Hydro & Nuclear Power Co., Ltd.

High-pressure mobile pump truck newly installed and operating method for the restart of Kori Nuclear Power Plant Unit 2. Korea Hydro & Nuclear Power Co., Ltd.

View original image

The facility is also equipped to draw seawater directly using a multi-articulated crane, then supply cooling water inside the containment building with a high-capacity mobile pump truck.


Director Choi Dongcheol explained, "In addition to 45 essential improvements in areas such as mechanical, electrical, and instrumentation systems, we independently upgraded about 60 additional pieces of equipment and made 480 improvements in the environmental sector." Currently, the only task remaining is the installation of the hydrogen removal equipment (PAR) inside the reactor.


High-capacity pump truck newly installed for the restart of Gori Nuclear Power Plant Unit 2. Korea Hydro & Nuclear Power

High-capacity pump truck newly installed for the restart of Gori Nuclear Power Plant Unit 2. Korea Hydro & Nuclear Power

View original image

Once all facility upgrades are completed, the Nuclear Safety and Security Commission, KINS, and Korea Hydro & Nuclear Power will conduct a pre-criticality meeting for a final inspection. If all conditions for nuclear plant operation are confirmed to be satisfied, the Nuclear Safety and Security Commission will approve criticality. Criticality means that the chain reaction of nuclear fission inside the reactor is maintained at a steady rate. Approval of criticality means that operation of the nuclear power plant is permitted.


The Nuclear Safety and Security Commission is expected to grant criticality approval at the end of March or in early April. After that, Korea Hydro & Nuclear Power will proceed with the restart of Kori Unit 2.


The continued operation of Kori Unit 2 is drawing greater attention amid the recent energy crisis triggered by the situation in the Middle East. The government has announced a policy to raise the nuclear power plant utilization rate to 80% as part of its response to the energy security crisis.



Chairman Choi Wonho emphasized, "With growing concerns about energy security due to the situation in the Middle East, it is crucial that facility upgrades and safety measures are implemented as planned to ensure the safe operation of Kori Unit 2 during its continued operation period."


This content was produced with the assistance of AI translation services.