Gyeonggi Province Expands "Yongin Semiconductor Power Grid Model" to All Cities and Counties... Revises Guidelines to Mandate Joint Construction
Gyeonggi Province Revises “Guidelines for Total Project Cost Management of Public Construction Projects”
Mandatory Consultations on Power and Water Infrastructure from the Planning Stage
Cost Reduction and Shortened Construction Period Expected for Public Projects
Gyeonggi Province has established an institutional foundation to expand the model of Local Road Route 318—which dramatically resolved the power supply issue for the Yongin Semiconductor Cluster—to cover all provincial projects.
On March 18, Gyeonggi Province announced that it will revise and promulgate the “Guidelines for Total Project Cost Management of Gyeonggi Province Public Construction Projects” in accordance with a special directive from Gyeonggi Governor Dongyeon Kim. Governor Kim had previously convened an emergency meeting with relevant departments, such as the Road Policy Division and Construction Safety Technology Division, on January 29 and instructed the amendment of these guidelines.
The revised guidelines were published in the Gyeonggi Province Gazette on March 18. The core provision is a new clause mandating joint construction consultations with the agencies responsible for underground utility facilities—such as Korea Electric Power Corporation and Korea Water Resources Corporation—from the “planning stage” when promoting public construction projects such as roads.
Specifically, the guidelines stipulate that consultations must take place before the official announcement of statutory plans (such as road construction plans), or before requesting a “feasibility study evaluation” from the Korea Research Institute for Local Administration for public construction projects with a total cost of KRW 50 billion or more.
The “Local Road Route 318 (Yongin–Icheon section, 27.02 km),” which served as the model for this institutionalization, is the first case in Korea to simultaneously build a new road and an underground power transmission network.
This approach offers several advantages: it shortens the construction period by five years (from ten years to five years) by streamlining administrative procedures and minimizing redundant work; reduces the total project cost by approximately 30 percent and improves the benefit-cost ratio (B/C); and fundamentally prevents community conflicts caused by the construction of transmission towers.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Lee Eunchul, Head of the Construction Safety Technology Division at Gyeonggi Province, stated, “We will continue to identify collaborative models in various administrative fields to ensure tangible benefits for residents of the province.”