[Issue] 'Rising Material and Labor Costs'... Construction Cost Settlement Dispute at Honam's Largest Coupang Logistics Center
Completed in 2024, Coupang 2 FC Logistics Center
Primary Contractor Adjusted Only Part of Contract Price Despite Rising Costs
Subcontractor Claims Losses of About 1.1 Billion Won in Labor and Other Expenses
The photo is unrelated to the specific facts of the article. It shows a Coupang camp in Seoul on the 10th of last month. Photo by Yonhap News Agency
View original imageAt the construction site of the Gwangju Coupang 2 Advanced Logistics Center, which Coupang completed as the largest facility in the Honam region, conflicts continue between the primary contractor and subcontractors due to unpaid construction costs and other issues. Since the COVID-19 pandemic, prices of materials, labor costs, and the general cost of living have risen sharply, causing the settlement amount to increase beyond the original contract price. However, disagreements over construction cost settlements among partner companies have resulted in years of disputes, prompting calls for urgent intervention by authorities.
According to the local construction industry on March 18, Coupang signed an agreement with Gwangju Metropolitan City in 2020 to build a large-scale logistics center in the Pyeongdong Industrial Complex area of Gwangsan District. The project, with a total investment of 112 billion won, was designed to cover a total floor area of approximately 168,000 square meters and have nine floors above ground. The center was completed in 2024, and Coupang pledged at the time to create 2,000 local jobs.
However, after the COVID-19 outbreak, the prices of materials, labor, and living expenses rose one after another, and it has been confirmed that the conflict over construction costs between the main contractor and subcontractors has persisted.
In one case, a subcontractor, Company A, requested a contract amount adjustment (ESC) from the primary contractor, Company B, due to price fluctuations caused by factors such as the COVID-19 pandemic and rising material and labor costs. However, most of these requests were denied.
This led to wage arrears at the construction site. In April 2023, the Gwangju-Jeonnam branch of the Korean Construction Workers' Union under the Korean Confederation of Trade Unions held a press conference claiming that about 300 workers who worked on this logistics center project had not received a total of around 690 million won in wages.
At that time, Company A demanded 1.47 billion won from Company B, but Company B paid only an additional 300 million won due to price fluctuations, according to Company A. Company A also had a contract with Company B at the Coupang site in Wonnchang-dong, Seo-gu, Incheon, and, at the request of the primary contractor, used 500 million won from the settlement amount of the Wonnchang-dong site to pay labor costs and other expenses at the Gwangju site.
Since 2022, Company A has sent official documents to Company B stating, "Despite suffering a severe deficit and financial difficulties, we did our best to complete the construction," and "We request that the appropriate settlement and interim payments be made reflecting the justified increase in costs due to inflation." However, according to Company A, they have not yet received proper settlement payments.
Furthermore, in April 2023, Company A reported Company B to the Regional Land Management Office for unfair construction practices, leading to the two sides signing a settlement agreement. The agreement stipulated that, in exchange for withdrawing the complaint, Company A would receive 200 million won under the name of inflation adjustment, and if Company B received additional payment due to price changes from the ordering party, 10% of that amount would be paid to Company A. Company B claims, however, that this did not reflect the actual losses incurred at all.
In particular, on February 27, the Korea Fair Trade Commission pointed out that Company B failed to notify Company A of the contract price increase received from the ordering party. As a result, the Commission issued a "warning" to Company B for violating the Subcontracting Act (failure to reflect design changes).
A representative of Company A said, "From the beginning of the project, there were many missing items in the construction details, so we requested design changes. As material and labor costs kept rising, we requested ESC from the primary contractor, but it was not accepted. In the end, we had to use our own company funds to pay workers' wages and forcibly complete the construction."
However, Company B maintains that it has fulfilled payment for the additional settlement amounts requested by the subcontractor.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
A representative of Company B stated, "For the additional construction costs requested by Company A, we made reasonable judgments and paid everything that was deemed appropriate. The claim that only a portion was reflected is a one-sided assertion by Company A, and even before we were notified of the contract price increase, we had already paid the subcontracting fees to Company A, including the increased amount."