Icheon City in Gyeonggi Province (Mayor Kim Kyunghee) announced on March 12 that it had conducted the 'Major Project Review for the First Half of 2026' to check the progress of key projects during the 8th local government term and to enhance the level of project completion.

Kim Kyunghee, Mayor of Icheon City, is conducting a "2026 First Half Major Project Review" to check the progress of key projects of the 8th elected government and to enhance the completeness of the projects. Provided by Icheon City

Kim Kyunghee, Mayor of Icheon City, is conducting a "2026 First Half Major Project Review" to check the progress of key projects of the 8th elected government and to enhance the completeness of the projects. Provided by Icheon City

View original image

This review was carried out over five sessions from March 6 to March 13, focusing on 41 social overhead capital (SOC)-centered projects, including 8th-term pledges and major ongoing issues. Of these, 31 projects underwent a written report review, while 10 projects were assessed through both written reports and on-site inspections for a comprehensive evaluation of their progress.


The review process involved the mayor receiving written reports on the status of project implementation in the city hall conference room, followed by direct visits to key project sites to check construction progress and identify any on-site difficulties.


The on-site inspections covered locations such as Sogori Park, Seongho Lake, the Women’s Vision Center, the site for the municipal crematorium, Daewol 2 General Industrial Complex, the Northern Sports Park, Jungpo-dong Sports Park, Jungpo District 3 Parking Lot, Bubal Hi-Pass Interchange, and Bubal Ami Area Public Parking Lot, among others.


Icheon City plans not only to confirm the current status of project implementation through this review, but also to discuss improvement measures aimed at enhancing process management and overall project completion. Additionally, any issues raised on-site will be reviewed immediately, with the city aiming to accelerate project progress and enhance citizens’ sense of tangible improvement.



Kim Kyunghee, Mayor of Icheon City, stated, "I will strengthen field-oriented administration by directly inspecting, inquiring about, and resolving whether projects are being prepared to the extent that citizens can truly feel the difference." She added, "We will speed up and further enhance the quality of projects, ensuring that they lead to changes citizens can experience, and I will see them through to completion with a strong sense of responsibility."