No Road? Then to the Sky... Cable Car Project Reshapes Mungyeong Tourism, Now on Track
Temporary ropeway to break through upper-section construction
A new logistics lifeline to open in May
The cable car development project that Mungyeong-si is promoting in the Mungyeong Sejae area has entered the foundational construction phase needed to overcome difficult sections, giving a clear boost to the project’s momentum.
Mungyeong-si Mungyeongsejae Cable Car Construction Project Fixed Anchor Device and Gubongbu Foundation Installation Work
View original imageThe city’s strategy is to overcome the limitations of restricted ground access caused by the rugged terrain through aerial transport, thereby achieving both schedule management and environmental conservation.
According to the city, it began installing a temporary ropeway last month that will be responsible for transporting materials. In light of the challenging conditions for building a road up to the upper station, materials will be moved via a cargo ropeway, while construction workers will travel via a passenger ropeway. This approach is being evaluated as a solution that minimizes unnecessary damage while maximizing construction efficiency.
The cargo ropeway aims to begin full operation in May after completing the construction of five towers and a machine room and conducting test runs. Installation is proceeding sequentially from Parking Lot No. 4 toward the upper section, with access road securing and logging work carried out simultaneously.
On-site infrastructure is also being put in place one after another. A field office for construction operations has been set up at Parking Lot No. 4, and concrete pouring has been completed for the drive unit foundations and wire fixed anchor devices. Once the first tower is erected this month, the structural work phase is expected to take on its full shape.
The main ropeway facilities are currently undergoing procurement cost review, and key equipment imported from overseas will be brought in step by step in line with the cargo ropeway operation schedule. Once the aerial logistics system stabilizes within the first half of the year, follow-up work such as main line construction is expected to proceed quickly.
On April 2, the city will hold a briefing session for residents at the Parking Lot No. 4 site to share the current status, future plans, and safety management measures. The aim is to enhance understanding of the project and broaden communication with the local community.
Mungyeong Sejae Cable Car Construction Project — Lower Terminal Access Road Construction, Partial Earthworks at Lower Terminal
View original imageAn official from the Mungyeong Sejae Management Office said, “This will be a turning point that strengthens the foundation for stay-type tourism through a new experiential route,” adding, “We will focus all our capabilities on high-quality construction and ensuring safety.”
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
The moment is approaching when a new axis of movement will be added above this traditional scenic site shaped by mountains and paths. Expectations are steadily growing regarding the impact it will have on tourism demand and the local economy.
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.