Installed capacity of 1.2 GW, total project cost of 3 trillion won
Up to 300 billion won in cost savings compared to the original plan

The Saemangeum floating solar power project, which had been delayed due to grid connection issues, will now move forward in earnest, aiming for early completion in 2029.


The Ministry of Climate, Energy and Environment announced that on the 9th it will sign a memorandum of understanding (MOU) for the "Early Promotion of the Saemangeum Floating Solar Power Project" at the Jeonbuk Special Self-Governing Province Office together with Jeonbuk Special Self-Governing Province, the Saemangeum Development and Investment Agency, Korea Hydro & Nuclear Power, and Korea Electric Power Corporation.


The Saemangeum floating solar power project is a key initiative to promote the development of the Saemangeum complex and attract core industries in the Jeonbuk region based on renewable energy. The first phase is a large-scale project with a total investment of 3 trillion won to install solar power generation facilities with an installed capacity of 1.2 GW (gigawatts) over a water area of approximately 13.5 square kilometers.


The acceleration of the project was made possible by improvements in the grid connection method. Initially, the power producer had to build a separate 15 km-long connection line to the inland grid. Recently, however, the grid connection point was changed to a high-voltage direct current (HVDC) converter station that is scheduled to be installed near the floating solar power facilities. As a result, the length of the connection line has been reduced to about 2 km, shortening it by 13 km compared to the original plan, and cost savings of 200 billion to 300 billion won are expected. The project’s economic feasibility is also expected to improve significantly.

Aerial view of the country's largest floating solar power plant (18.7 MW) built in Bieungdo-dong within the Gunsan 2 National Industrial Complex in Gunsan, Jeonbuk. Yonhap News.

Aerial view of the country's largest floating solar power plant (18.7 MW) built in Bieungdo-dong within the Gunsan 2 National Industrial Complex in Gunsan, Jeonbuk. Yonhap News.

View original image

In addition, instead of using a nearby public transmission line that was originally planned to be built by 2031, the parties agreed through this MOU to build and connect an inland overland transmission line earlier, by 2029. By promoting power generation facilities, transmission and transformation facilities, and grid connection simultaneously, the overall project schedule is expected to be moved forward.


The organizations to the MOU plan to accelerate the project by strengthening cooperation throughout the entire process, from the installation of power generation facilities to the construction of transmission and transformation facilities and grid connection. The Ministry of Climate, Energy and Environment and Korea Electric Power Corporation will closely manage the power grid construction schedule and grid connection procedures to ensure timely interconnection.



Minister of Climate, Energy and Environment Kim Sunghwan said, "This agreement is an important turning point for Saemangeum to leap forward as a global hub for renewable energy," adding, "We will provide active support so that the project can proceed without setbacks and reinvigorate the regional economy of Jeonbuk."


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.

Today’s Briefing