Formation of CAIC amid dispute over responsibility for tunnel collapse
Re-examining causes of opening delay

The Ministry of Land, Infrastructure and Transport has formed a Construction Accident Investigation Committee (CAIC) to identify the causes of the delay and verify the safety of the Bujeon-Masan double-track railway, whose opening has been postponed for the fifth year due to a ground subsidence accident, and has launched a full-scale investigation.

An 18-meter-wide ground subsidence occurred at the construction site of the Bujeon-Masan double-track light rail section. Photo by Busan Police Agency

An 18-meter-wide ground subsidence occurred at the construction site of the Bujeon-Masan double-track light rail section. Photo by Busan Police Agency

View original image

On the 5th, the ministry held a kick-off meeting for the CAIC at the Yeongnam Regional Headquarters of the National Railroad Corporation and announced that it had officially launched the investigation committee composed of external experts. The CAIC includes members of the Construction Accident Investigation Committee Group, the Korea Authority of Land & Infrastructure Safety, and experts in geotechnical engineering, foundations, structures, and construction. The investigation will run for about four months until June 4, and may be extended if necessary.


The Bujeon-Masan double-track railway, which connects 51.1 km from Bujeon Station in Busan to Masan Station in South Gyeongsang Province, began construction in 2014 as a private investment project and was scheduled to open in February 2021. However, in March 2020, a ground subsidence accident occurred during construction of an evacuation passage in the Nakdong River under-river tunnel (Nakdong Tunnel No. 1), halting the project at a 99% completion stage. The project period has currently been extended until the end of December this year.


After the accident, Smart Rail, the project operator, conducted two internal investigations and concluded that the cause of the accident was an "act of God" due to poor ground conditions, rather than problems with the construction method. The Ministry of Land, Infrastructure and Transport and the National Railroad Corporation also formed separate investigation teams to verify this, but they explained that at the time they were unable to systematically identify the cause due to limitations in data and access to the site.


Subsequently, Smart Rail refused to construct two remaining evacuation passages that are still unbuilt, citing similar ground conditions to the accident section, which has continued to delay the opening. More recently, the conflict has been prolonged as the company has even filed a lawsuit against the government over the cost of restoration work for the tunnel collapse.


Through this CAIC, the ministry plans to reinvestigate the cause of the accident in a professional and objective manner and to establish a reasonable basis for deciding whether to resume construction. It also plans to draw up measures to prevent a recurrence through reviewing the accident investigation report submitted by the project operator, examining design documents, and holding hearings with related parties.



The ministry stated, "We will manage the process closely so that the operation of the CAIC does not cause any additional delays to the opening schedule," adding, "We will also prepare institutional and technological measures to prevent similar accidents."