DL E&C Excavates 43-Story Vertical Tunnel...Utilizes Cutting-Edge "RBM Method"
Excavating a 120-Meter Vertical Tunnel the Height of a 43-Story Building
Completed in Just Seven Months Using the RBM Method
Lower Risk of Fall Accidents and Shorter Construction Period
DL E&C announced on the 4th that it has completed excavation work in just seven months for the "Phase 2 construction of the port hinterland complex at the northern container berth of Busan New Port," which is underway at Yokmang Mountain in Busan.
The project aims to use rock obtained by removing Yokmang Mountain as reclamation material for Busan New Port and Jinhae New Port, with completion targeted for 2034. It is the largest single construction project since the opening of Busan New Port in 2006.
At the vertical tunnel inside the construction site for the Phase 2 port hinterland complex at the north-side container quay of Busan New Port, a DL Engineering & Construction official is directing excavation work. Photo by DL Engineering & Construction
View original imageThe core of this project is to excavate a mountain peak equivalent to a 43-story building and construct a 120-meter vertical tunnel. This tunnel serves as a passageway for transporting rock. Excavating an ultra-deep vertical tunnel more than 100 meters underground is considered a highly challenging construction task. DL E&C proposed to the client, Busan Port Authority, the use of the RBM (Raise Boring Machine) method employing state-of-the-art excavation equipment, and is carrying out the project on a turnkey basis.
The RBM is a large piece of equipment that bores through bedrock by rotating a head fitted with dozens of cutting blades. Unlike conventional methods that dig down from the surface, this method places the equipment underground and rotates it upward to excavate. It reduces the risk of fall accidents during construction and can shorten the construction period by 30% compared to traditional methods. Over the past five years, DL E&C has been the only company in Korea with a track record of applying the RBM method.
With the recent surge in ultra-deep infrastructure projects such as pumped-storage power plants and the GTX (Great Train Express) metropolitan express railway, the use of the RBM method has been expanding as well. In addition to the RBM method, DL E&C has developed new technologies related to vertical tunnel construction, for which it has filed patent applications and is pursuing commercialization.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Park Sangshin, CEO of DL E&C, said, "Based on the technological know-how accumulated through numerous vertical tunnel projects such as the Yeongdong Pumped-Storage Power Plant and GTX-A, we are leading the mechanization of construction and the advancement of technology," adding, "Through the RBM method, we will continue to maintain our overwhelming technological leadership in the pumped-storage power sector."
© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.