"380,000 Residents in 4 Local Governments... Essential for Preparing for Extreme Heavy Rainfall"

Gwangmyeong City in Gyeonggi Province announced on the 3rd that it had asked the central government to expand the number of retention basins for Mokgamcheon from the currently planned one to three, in order to fundamentally prevent flood damage along Mokgamcheon caused by recurring localized heavy rainfall.


On this day, Gwangmyeong City Vice Mayor Choi Hyemin attended the Social Overhead Capital (SOC) Subcommittee meeting of the preliminary feasibility study of the Ministry of Economy and Finance, held at the main building of the Korea Development Institute (KDI) in Sejong Special Self-Governing City, and requested approval of the original preliminary feasibility study plan for the "Mokgamcheon River Maintenance Project Phase 2," which includes plans to construct the Mokgamcheon R2 and R3 retention basins.

Retention basin development plan for the Mokgamcheon area. Provided by Gwangmyeong City.

Retention basin development plan for the Mokgamcheon area. Provided by Gwangmyeong City.

View original image

Vice Mayor Choi conveyed this position, stating, "Approximately 380,000 residents live along both banks of Mokgamcheon, within sections under the jurisdiction of four local governments: Gwangmyeong, Siheung, Bucheon, and Guro District in Seoul."


Mokgamcheon is a national river that is a tributary of Anyangcheon, itself a tributary of the Han River. It originates in Siheung, flows through Gwangmyeong City, and then joins Anyangcheon. Its channel length is 12.33 km, and its basin area is 55.58 square kilometers.


The city explained that, in the urban section of the downstream reach of Mokgamcheon, the available retention capacity within the river channel is 2.1 million cubic meters per second, which falls far short of the planned flood discharge of 765 cubic meters per second, leaving the flood control conditions highly unstable.


Currently, as part of the Mokgamcheon River Maintenance Project, the Han River Basin Environmental Office is proceeding with the reconstruction of bridges and the construction of the "R1 retention basin" with an area of 249,745 square meters in the Okgil-dong area of Gwangmyeong City. For the R1 retention basin, land compensation procedures are now underway, and construction is scheduled to begin this year with completion targeted for 2029.


However, it is assessed that relying solely on the R1 retention basin would only allow for a response to floods with a 30-year return period, making it insufficient to cope with recurring extreme heavy rainfall. Accordingly, the Han River Basin Environmental Office is additionally planning the construction of the "R2 retention basin," with an area of 169,725 square meters in the Noonsa-dong area of Gwangmyeong City, and the "R3 retention basin," with an area of 63,803 square meters in the Gahak-dong area of Gwangmyeong City.


The R2 and R3 retention basins are regarded as key flood control facilities to prevent urban inundation damage in large-scale development areas such as the Gwangmyeong-Siheung New Town and the Gwangmyeong-Siheung Technovalley, which are being developed in the midstream and upstream sections of Mokgamcheon.



Based on the discussions at this SOC Subcommittee meeting, the results of the preliminary feasibility study for the R2 and R3 retention basin construction project are scheduled to be announced sometime between March and April.


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.

Today’s Briefing