Completion Date Set Five Years After Collapse
Current Progress at 63 Percent as Finishing Work Continues
Schedule Adjusted After Controversy Over Retaining Commercial Floor

The construction of the Gwangju Hwajeong I-Park, which resulted in seven casualties due to a collapse accident, is expected to be completed and ready for occupancy in January 2027 after a full demolition and reconstruction. This comes five years after the accident, and the project is currently in its final stages.

Seogu District Hwajeong I-Park Construction Site. Photo by Seogu District

Seogu District Hwajeong I-Park Construction Site. Photo by Seogu District

View original image

According to Seogu District in Gwangju and HDC Hyundai Development Company (HDC Hyundai Development), as of February 1, the Hwajeong-dong I-Park is being rebuilt as the "Gwangju Centennial I-Park," with the construction progress currently at 63%. All framework construction has been completed, and major finishing work, both interior and exterior, is underway.


HDC Hyundai Development initially announced its plan to fully demolish and reconstruct the accident site following the collapse in January 2022, projecting completion by December 2027. However, as plans emerged to retain part of the commercial floor where neighborhood facilities would be located, prospective residents voiced strong opposition.


While HDC Hyundai Development had promised a full demolition, the company later revised its plans after discussions with prospective residents, agreeing to retain the above-ground portion of the commercial floor due to concerns about an excessively long construction period. As a result, the completion date was moved up to the first half of 2027.


With construction conditions remaining relatively stable since then, it is now expected that occupancy will be possible in January 2027. As this is the first case in Korea of full demolition followed by reconstruction, HDC Hyundai Development initially set a generous construction timeline. However, as complaints about dust and noise during the construction process were fewer than anticipated, the overall schedule has been shortened.


HDC Hyundai Development shared the current construction progress and future schedule with prospective residents at a briefing session held on January 24. A company representative stated, "We will provide further details on the exact move-in date and procedures three months prior to occupancy," adding, "We will prioritize safety and quality until the very end of the project."



Previously, on January 11, 2022, at the Hwajeong-dong I-Park construction site in Seogu District, Gwangju, the floors and ceilings from the 39th to the 23rd stories, as well as internal and external structures, collapsed simultaneously, resulting in the deaths of six workers and injuries to one.