Hwaseong City Eases Dongtan Tram Bidding Requirements and Relaunches Tender
Construction Period Extended by 10 Months, Budget Increased by 1.5%
Underground Utility Relocation Costs Included as Post-Settlement Item
Hwaseong City in Gyeonggi Province is making another attempt to select a contractor for the Dongtan Urban Railway (Dongtan Tram) project by easing the bidding requirements, after previous bidding rounds repeatedly failed.
A bird's-eye view of the Dongtan Urban Railway (Dongtan Tram) connecting major areas of Hwaseong Dongtan New City centered around Dongtan Station. Hwaseong City has relaxed the bidding conditions for the first phase of the Dongtan Tram construction and has relaunched the bidding process. Provided by Hwaseong City
View original imageHwaseong City announced on the 30th that, in order to promptly resume the Dongtan Tram project, it has completed improvements to the bidding conditions and, on the 29th, finalized the contract request for construction procurement and tendering.
This new bidding round comes just one month after the DL E&C consortium, which was the sole bidder for the first phase of the Dongtan Tram construction at the end of last month and was pushing for a private contract, announced its intention to withdraw from the project.
Immediately after the contract process was halted, the city convened an emergency countermeasure meeting and gathered feedback from experts and the construction industry through a roundtable, subsequently improving the bidding conditions.
For this bidding, the city designated the cost of relocating underground utilities-an unpredictable expense during construction-as a post-settlement (PS) item, shifting the risk management responsibility directly to the city.
In addition, to reflect the construction environment of the tram project, including the relocation of urban obstacles, the construction period was extended by 10 months from the original 43 months to 53 months. The construction budget was also increased by 1.53%, from 683.4 billion won to 693.2 billion won, to account for inflation.
The city plans to ensure the smooth progress of the new bidding process by improving the bidding conditions and will focus its administrative capabilities on normalizing the Dongtan Tram construction project, with the goal of commencing priority construction in the second half of the year.
Jung Myung-geun, Mayor of Hwaseong City, stated, "We proactively reviewed and boldly incorporated the suggestions of experts and the construction industry regarding the key issues raised during the project process into the improved bidding conditions. We will take responsibility to ensure the project proceeds stably, aiming to begin priority construction as soon as possible."
The Dongtan Tram is a project to build a streetcar line connecting major areas of Dongtan New City, centered around Dongtan Station, which serves both the GTX-A and SRT lines. The tram will span a total length of 34.2 kilometers and include 36 stations. The route consists of 'Route 1,' which runs 16.4 kilometers from Mangpo Station in Suwon to Dongtan Station and Osan Station, and 'Route 2,' which covers 17.8 kilometers from Byeongjeom Station to Dongtan Station and the vehicle depot.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
The sections included in this re-bidding for the first phase of construction are the Mangpo Station-Dongtan Station-Banggyo-dong route (13.8 kilometers) and the Byeongjeom Station-Dongtan Station-vehicle depot route (17.8 kilometers). The 2.85-kilometer section from Banggyo-dong to Osan Station, which lies within Osan City and was excluded from the first phase, will be pursued as phase two in accordance with the schedule of the 'Unamttul AI City Urban Development Project' currently being promoted by Osan City.