Current Executive Board and Emergency Committee Propose Separate Timelines for Normalization and Dismissal
Executive Board: "A Decision Must Be Made Before It’s Too Late"... Six Key Normalization Measures Submitted for Vote
Emergency Committee:

A view of the sluggish redevelopment site in Singa-dong, Gwangsan-gu, Gwangju. Photo by Kim Wanjung

A view of the sluggish redevelopment site in Singa-dong, Gwangsan-gu, Gwangju. Photo by Kim Wanjung

View original image

On the afternoon of January 27, at the Singadong housing redevelopment project site in Gwangsan-gu, Gwangju, a member of the association who said they had lived in Singadong for over 30 years gazed at the cleared land for a long time before shaking their head. "I can no longer even guess when this place will finally become an apartment complex."


This member said they remembered nearly the entire process since the project was first discussed. While the area had been designated as a redevelopment zone, permits had been obtained, and demolition completed, there had been a long period of uncertainty about what would come next. "We already replaced the association head once last February. But now, seeing talk of another dismissal, I am growing increasingly worried."


The Singadong housing redevelopment and maintenance project is the largest redevelopment project in Gwangju, yet it has failed to break ground for 15 years since the area was designated as a redevelopment zone in 2011. Even after relocation and demolition were completed, the project site remains an empty lot, and internal conflicts over how to normalize the project have resurfaced within the association.


Singa Redevelopment Stalled for 15 Years, Site Remains Idle Even After Demolition

The Singadong housing redevelopment and maintenance project began in 2011 when the Singadong area in Gwangsan-gu, Gwangju, was designated as a redevelopment zone. The project aims to construct an apartment complex with three basement levels and 29 above-ground floors, totaling 4,718 units (including 403 rental units), with a total project cost of approximately 1.8 trillion won. The association completed major approval procedures by obtaining project implementation approval in 2018 and management disposition approval in 2020.


However, conflicts with the construction company over sales prices and construction costs, as well as internal disagreements within the association, repeatedly delayed the groundbreaking. Although relocation and demolition were completed in 2023, the project still failed to gain momentum. Between 2023 and 2024, the association made several attempts to select an alternative construction company to normalize the project, but these efforts were unsuccessful, leaving the project site vacant for an extended period.

On the afternoon of February 22 last year, a member of the Shin-Gadong Housing Redevelopment Association was examining a ballot paper at the dismissal general meeting of the association's executive committee held at the Kim Dae-jung Convention Center in Gwangju. The general meeting was hosted by the Shin-Ga Redevelopment Normalization Promotion Committee, with a total of 849 members participating, including those who submitted written resolutions and on-site voters. The motion to dismiss the association head was passed with 836 votes in favor, 3 against, and 10 abstentions. Photo by Bohyun Song

On the afternoon of February 22 last year, a member of the Shin-Gadong Housing Redevelopment Association was examining a ballot paper at the dismissal general meeting of the association's executive committee held at the Kim Dae-jung Convention Center in Gwangju. The general meeting was hosted by the Shin-Ga Redevelopment Normalization Promotion Committee, with a total of 849 members participating, including those who submitted written resolutions and on-site voters. The motion to dismiss the association head was passed with 836 votes in favor, 3 against, and 10 abstentions. Photo by Bohyun Song

View original image

As the project delays dragged on, internal conflicts within the association accumulated. In 2025, the executive board was replaced through a general meeting of association members, and the new board began renegotiations with the construction company and efforts to normalize the project. However, ongoing debates over sales prices, construction costs, and project structure have prevented any clear breakthrough.


Against this backdrop, when the executive board proposed the "Six Key Measures for Project Normalization" as an agenda item for the general meeting this February, some members of the association also began demanding the dismissal of the association head and executives.


The extraordinary general meeting to dismiss the association head, auditor, and directors will be held at 7 p.m. on February 6 on the second floor of the exhibition hall at the Kim Dae-jung Convention Center. The following day, February 7, at 2 p.m., another extraordinary general meeting organized by the current executive board will be held at the same location.


Executive Board: "No Groundbreaking Without Resolving Delays"... Background of the 'Six Key Measures' Proposal

The current executive board maintains that the "Six Key Measures for Project Normalization," which require a vote by association members, are an unavoidable choice to resolve the prolonged delays and create conditions for groundbreaking. They believe that unless uncertainties surrounding sales prices and construction costs are reduced and the risk of unsold units is managed in advance, the project could face even further delays.


The measures proposed by the executive board include adjusting the association members' sales price to at least 60% of the general sales price and allocating a budget for unsold unit countermeasures. The board explained that adjusting the members' sales price is intended to alleviate short-term burdens and enhance the competitiveness of general sales, thereby reducing the risk of unsold units. They also emphasized that the budget for unsold unit countermeasures would be refunded to members if all units are sold, thereby reducing the final contribution amount.

Perspective view of the residential redevelopment project in Singadong, Gwangju.

Perspective view of the residential redevelopment project in Singadong, Gwangju.

View original image

Regarding the method for setting general sales prices, the board noted that overly optimistic high prices in the past had led to project delays, and going forward, they plan to apply objective standards based on real estate market analysis, including supply, occupancy, and unsold unit data. On the matter of using a unified brand and construction method, the board stated that ensuring an early groundbreaking and project stability takes precedence over brand selection.


Association head Byungseok Han said, "At the extraordinary general meeting, I will thoroughly explain to members the circumstances and key issues that caused project delays due to conflicts with the construction company, Bitgoeul Dream Project Group." He added, "Last year, negotiations were nearly impossible due to opposition from some board members." He stated that he plans to include the motion to dismiss certain board members among the main agenda items at this general meeting.


Emergency Committee: "Six Key Measures Could Increase Burdens"... Citing Unfulfilled Promises and Procedural Issues

The Emergency Committee, which is calling for the dismissal of association executives, cited the fulfillment of campaign promises and overall management issues as grounds for dismissal in its petition to convene the general meeting. The petition stated that the association head's campaign promises of a construction cost of 6.3 million won per pyeong and groundbreaking within the year had not been fulfilled and were deemed unlikely to be realized in practice.


Additionally, the petition pointed out that, regarding construction of maintenance infrastructure, unverified information and content unfavorable to the association had been provided to the media, damaging the association's image and, as a result, infringing on members' property rights. It also cited procedural issues, such as the attempt to appoint an additional full-time director and apply retroactive pay, even though the operating budget for only one full-time director had been approved at the June 2025 general meeting.

Redevelopment site of Singadong. Photo by Bohyun Song

Redevelopment site of Singadong. Photo by Bohyun Song

View original image

The negotiation process with the construction company was also cited as a reason for dismissal. The petition expressed concern that the so-called "Six Key Measures" were being put to a general meeting without adequate safeguards, which could place a significant burden on the association if negotiations break down in the future.


Jo Youngmoo, head of the Singa Redevelopment Emergency Committee, argued, "If the Six Key Measures are passed, there could be a greater risk of rising construction costs and uncertainty over the groundbreaking timeline. Such burdens could result in considerable disadvantages for association members." He added, "We plan to hold a project briefing session at 2 p.m. on January 31 at the Kim Dae-jung Convention Center to explain the project's direction and structure following the dismissals."


Members Divided Over Dismissal or Retention of Executives

Opinions among association members are divided. One member, who requested anonymity, said, "After replacing the previous association head at the dismissal meeting last February, we have operated under new leadership for just over seven months, and now there is talk of another dismissal. I wonder whether constantly changing leadership in such a large-scale project is truly helpful."



Another member said, "While I agree with some of the issues raised by the Emergency Committee, considering the recurring procedures like the annual guarantee from the Housing and Urban Guarantee Corporation (HUG), it would be difficult to build trust in the project if internal turmoil continues."