Phase 2 of Full Reconstruction Nears Completion
Minimizing Citizen Inconvenience by Maintaining Eight-Lane Traffic
Final Completion Targeted for July 2027
Cantilever Structure Removed, Reborn as a Girder Bridge

Seongnam City in Gyeonggi Province (Mayor: Shin Sang-jin) announced on January 22 that it plans to open the Bundang-bound section of the completely reconstructed Sunae Bridge in July 2026 as a priority.

Overview of the complete reconstruction work of Sunaegyo Bridge. Provided by Seongnam City

Overview of the complete reconstruction work of Sunaegyo Bridge. Provided by Seongnam City

View original image

The complete reconstruction of Sunae Bridge, with a total project cost of 36.9 billion won, is being carried out in sequential phases to maintain eight lanes of two-way traffic and minimize inconvenience for citizens.


As part of the first phase, Seongnam City completed the installation of a temporary bridge for Bundang-bound traffic detour in February 2025. Currently, vehicles are using a temporary four-lane road.


The second phase, currently underway, involves demolishing the existing Bundang-bound bridge and constructing a new one. The city plans to complete this process by July 2026 and open the Bundang-bound section first.


In the third phase, the Seoul-bound bridge will be demolished and rebuilt. The entire project is scheduled for final completion in July 2027.


Sunae Bridge received an E grade (poor) for structural defects following an emergency detailed safety inspection in 2023, which led to a period of total closure. Although Seongnam City resumed traffic after conducting urgent temporary reinforcement work, it concluded that a fundamental solution was needed to ensure safety, resulting in the decision for a complete reconstruction.


The core focus of this reconstruction is to enhance structural safety. The problematic cantilever structure, which was cited as an issue during the past Jeongja Bridge sidewalk collapse, will be completely eliminated. Instead, the city will apply the proven girder bridge method to transform Sunae Bridge into a safe structure that citizens can use with confidence.


During the construction period, the city is working closely with related agencies, including the Bundang Police Station, to minimize traffic congestion. It is also strengthening safety facilities and improving pathways along the Tancheon Stream to ensure the safety of pedestrians and cyclists, making every effort to manage on-site safety.



A Seongnam City official stated, "The complete reconstruction of Sunae Bridge is a project that prioritizes citizen safety above all else. We ask for your understanding regarding any inconvenience during the construction period," adding, "We will complete the project quickly and safely by the final completion date in July 2027."


This content was produced with the assistance of AI translation services.

© The Asia Business Daily. All rights reserved. Unauthorized AI training and use prohibited.

Today’s Briefing