Expanding Supporting Ports and Adding Installation Vessels: "Supplying 4GW of Offshore Wind Power Annually"
Announcement of Pan-Government Offshore Wind Power Infrastructure Expansion and Supply Plan
Expansion of Supporting Ports Including Pohang Yeongilman Port and Saemangeum New Port
Additional WTIV Construction by Hanwha and Korea Electric Power Corporation
Financial Support Utilizing 150 Trillion Won National Growth Fund
Consideration of Contract Extension, Price Indexation, and CfD Implementation
Offshore Wind Power Auction in First Quarter Next Year After Military Operational Review
Offshore wind turbines installed at the Nakwol Offshore Wind Power Complex in Yeonggwang, Jeollanam-do. Samhae ENC
View original imageThe government has announced plans to expand infrastructure such as supporting ports and installation vessels (WTIVs) to lay the foundation for supplying 4 gigawatts (GW) of offshore wind power annually. The offshore wind power auction will be conducted in the first quarter of next year, after reviewing military operational feasibility for all projects that have received generation permits. In the long term, the government will reform the auction system by extending contract periods, introducing price indexation, and implementing a Contracts for Difference (CfD) scheme.
On the morning of December 10, the Ministry of Climate, Energy and Environment held the second meeting of the 'Pan-Government Offshore Wind Power Supply Acceleration Task Force (TF)' at the Irum Center in Yeouido, Seoul, and, together with relevant ministries, announced the 'Plan for Expanding Offshore Wind Power Infrastructure and Supply.'
This meeting brought together relevant ministries such as the Ministry of Oceans and Fisheries, the Ministry of National Defense, and the Financial Services Commission, as well as domestic and international developers and manufacturers. They discussed concrete implementation plans to supply over 25GW of offshore wind power cumulatively by 2035 and to reduce the levelized cost of electricity to below 150 won per kilowatt-hour (kWh).
The global offshore wind power market is expected to grow from 83GW in 2024 to 441GW by 2034. In contrast, only 0.35GW of offshore wind capacity is currently in commercial operation domestically, due to insufficient supporting infrastructure, difficulties in securing financing, complex permitting procedures, and challenges with local acceptance.
The meeting focused on expanding key infrastructure for offshore wind power construction, such as supporting ports, installation vessels, and financial resources.
Currently, the only port that can effectively support offshore wind power is Mokpo New Port. The government plans to adjust the functions of existing ports and develop new supporting berths in parallel, aiming to establish a port system capable of handling 4GW annually by 2030.
In the short term, the government will reinforce the bearing capacity (the ability of the ground to safely support loads) of ports such as Pohang Yeongilman Port and Saemangeum New Port to expand their functions to support offshore wind construction. In the long term, the Ministry of Oceans and Fisheries will reflect plans for developing new offshore wind supporting berths at Incheon Port, Gunsan Port, and others in the 4th National Port Master Plan, which will be announced early next year.
After 2030, not only Mokpo New Port but also Incheon Port, Gunsan Port, Saemangeum New Port, Haenam Hwawon Industrial Complex, Pohang Yeongilman Port, Ulsan Port, and Samcheonpo Port are expected to serve as supporting ports for offshore wind power.
Regarding installation vessels used to install offshore wind turbines at sea, the government aims to secure at least four 15-megawatt (MW) class vessels by 2030 by encouraging both private and public investment.
In line with this, Hanwha is currently constructing a 15MW-class installation vessel, targeting deployment at the Shinan Ui Offshore Wind Power Complex in June 2028. Korea Electric Power Corporation is also pursuing a plan to jointly invest with the private sector to build a 15MW-class installation vessel by 2029.
Currently, there are two installation vessels in operation domestically: Hyundai Frontier (10MW class) and Hansan No.1 (10MW class). The Ministry of Climate, Energy and Environment announced plans to secure a total of more than six installation vessels after 2030, establishing the foundation to supply 4GW annually.
On the financial side, the government plans to utilize the 150 trillion won National Growth Fund and the Future Energy Fund, which was created through joint investments by financial institutions. The Future Energy Fund, funded by Industrial Bank of Korea, KB Kookmin Bank, Shinhan Bank, Hana Bank, Woori Bank, and Nonghyup Bank, has completed the first-stage fund formation of 1.26 trillion won and plans to invest in its first project next year. The Future Energy Fund aims to raise 9 trillion won by 2030.
The Ministry expects that by expanding the supply infrastructure, it will be possible to complete and start construction on a cumulative total of 10.5GW by 2030, and supply a cumulative total of 25GW by 2035.
The government plans to conduct a fixed-price contract competitive auction for offshore wind power in the first quarter of next year, after reviewing military operational feasibility for all project sites that have received generation permits. This approach is intended to prevent project delays caused by military operational reviews after a developer has been selected through the auction.
The Ministry also plans to raise the effective competition ratio of next year's competitive auction to at least 2:1, thereby encouraging a gradual reduction in electricity generation costs.
In addition, through research studies, the government will consider measures such as extending the fixed-price contract period from the current 20 years to 25 years, introducing price indexation in line with the revision of the Renewable Portfolio Standard (RPS), and adopting the Contracts for Difference (CfD) scheme that contributed to reducing offshore wind power costs in the United Kingdom.
To improve investment predictability for companies, the Ministry will announce the '2035 Offshore Wind Power Long-Term Auction Roadmap' in the first half of next year. The auction volume will be reviewed and re-announced every three years, taking into account industry demand and effective competition ratios. The government will also pursue cost reductions by establishing energy hubs near offshore wind complexes to eliminate duplication of shared transmission networks and connection facilities.
To strengthen the execution of offshore wind power projects, the government will establish a director-level organization called the 'Offshore Wind Power Promotion Team' and launch it within this year. In addition, in line with the implementation of related laws in March next year, the government will begin selecting planned sites with reduced permitting burdens and plans to conduct site auctions starting in 2029. Through these measures, the average project period, which currently takes about 10 years, is expected to be shortened to within 6.5 years.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
To secure local acceptance, the government announced plans to institutionalize resident participation by introducing a 'Wind Income Standard Model' to share offshore wind power profits with local communities.