The Yuseong Complex Terminal in Daejeon will hold its completion ceremony on the 29th and begin operations in January next year.


Located within the Yuseong Metropolitan Transfer Center, the Yuseong Complex Terminal was built with a total project cost of 44.9 billion won. It covers a land area of 15,000 square meters and has a total floor area of 3,858 square meters, accommodating up to 6,500 users per day.


Starting in January next year, intercity and express buses on 32 routes-including Seoul, Cheongju, and Gongju-will operate from the terminal. At the same time, the currently used Yuseong Intercity Bus Stop building will be remodeled, with renovations scheduled for completion by April.


The terminal offers strong connectivity with various public transportation options, including Subway Line 1 and the Bus Rapid Transit (BRT) system. Its proximity to the Yuseong Interchange positions it as a key gateway to the northwestern region of Daejeon.


Perspective view of Yuseong Complex Terminal (Photo by Daejeon City)

Perspective view of Yuseong Complex Terminal (Photo by Daejeon City)

View original image

In addition, the surrounding area includes a 17,000-square-meter site designated for support facilities to attract convention and other complex facilities, as well as a 7,000-square-meter site reserved for future public office relocations. Through integration with public transportation, these developments are expected to invigorate local businesses and create jobs, generating positive effects for the regional economy as a whole.


The construction of the Yuseong Complex Terminal was first initiated in 2010 through a private sector bidding process, but all four attempts failed, causing the project to stall for an extended period.


Subsequently, considering ongoing declines in passenger demand and a downturn in the housing market, the city shifted its development strategy in February 2023 by directly investing municipal funds to build a public terminal focused on passenger facilities, leading to the start of construction.


Daejeon City gathered and reflected feedback from local terminal and transportation operators at each stage of planning, design, and construction. For stable terminal operations, Daejeon Transportation Corporation and a private operator will jointly manage and operate the facility.



Nam Sideok, Director of the Daejeon City Transportation Bureau, stated, "The Yuseong Complex Terminal was completed within three years of the revised development plan, thanks to swift policy decisions and public-private cooperation. We will ensure that all remaining procedures are completed smoothly before the terminal opens next month."