Court Also Grants Suspension of Enforcement Requested by Kyeryong Construction

SK Ecoplant announced on the 26th that the Seoul Administrative Court has approved its request to suspend the enforcement of a business suspension order related to the collapse accident at a road construction site in Siheung, Gyeonggi Province, in April last year.


Accordingly, SK Ecoplant stated that its business operations will not be affected until 30 days after the verdict date of the ongoing main lawsuit seeking to revoke the administrative disposition.


On April 30 last year, a girder (a type of beam installed under the bridge deck) being installed at the construction site of the West Coast Bypass Road in Sihwa MTV, Wolgot-dong, Siheung, collapsed, resulting in the death of one worker in his 50s, and injuries to five other workers and one citizen.


Court Approves Suspension of Business Suspension Order for SK Ecoplant over 'Siheung Collapse Accident' View original image

At the time, the construction was handled by SK Ecoplant and Kyeryong Construction, which formed a consortium with SK Ecoplant. The police referred six individuals, including the SK Ecoplant site manager, and two subcontractor officials to the prosecution on charges of occupational negligence resulting in death or injury.


The Ministry of Land, Infrastructure and Transport also held the two companies accountable for the accident and notified them last month of a six-month business suspension, effective December 1 of this year. Both companies responded with legal action, filing for suspension of enforcement and lawsuits to revoke the business suspension order.



The court also approved the request for suspension of enforcement filed by Kyeryong Construction.


This content was produced with the assistance of AI translation services.