Administrative Lawsuit Filed by Residents Over Eco-Friendly Integrated Town Site Dismissed
Court Rules Administrative Procedures Were Lawful
City Administration Focuses on Resolving Resident Conflicts and Advancing Facility Construction

Regarding the installation of the eco-friendly integrated town promoted by Sejong City, the Daejeon District Court on the 20th dismissed the administrative lawsuit filed by local residents and ruled in favor of the executive branch.

Regarding the installation of the eco-friendly integrated town promoted by Sejong City, the Daejeon District Court on the 20th dismissed the administrative lawsuit filed by local residents and ruled in favor of the executive branch.

View original image

The residents of Songsong-ri, Jeondong-myeon, Sejong City, who had formed a committee to oppose the construction of a waste incineration plant and had waged a strong protest movement for several years, have now received a court ruling regarding the installation of the eco-friendly integrated town.


The court determined that both the designation of this area as the site for the eco-friendly integrated town and the administrative procedures leading up to the site selection were lawful.


According to Sejong City and the Daejeon District Court on November 20, the court dismissed the administrative lawsuit filed by the Committee Against the Incineration Plant, which sought to nullify the disposition announcing the site selection for the waste treatment facility. The first trial verdict, delivered on this day, followed two years of proceedings after residents, as members of the committee, filed the lawsuit in July 2023, claiming that the city's waste treatment facility project violated relevant laws.


The court ruled that Sejong City had lawfully conducted the site selection process and methods for the eco-friendly integrated town based on the Act on the Promotion of Installation of Waste Treatment Facilities and Support for Surrounding Areas and other related laws.


With the court's ruling confirming the legitimacy of the administrative procedures for the eco-friendly integrated town, the city plans to promptly push forward with the waste treatment facility installation project.


The eco-friendly integrated town project was initiated in response to a sharp increase in daily household waste due to population growth and a lack of in-house treatment facilities, which has led to annual private outsourcing costs reaching hundreds of billions of won. The city plans to build an incineration facility with a daily capacity of 480 tons, with a total project cost of approximately 360 billion won and a site area of 65,123 square meters. The facility will also include amenities desired by residents, such as a swimming pool and bathhouse, as well as cultural and experiential facilities.


A city official stated, "In March 2021, candidate sites for the waste treatment facility were selected, and in July 2023, the site in Songsong-ri, Jeondong-myeon was officially designated. During this process, we held resident briefings and explanatory sessions, and organized tours of waste treatment facilities to provide factual information. We also operated a resident support task force to help resolve conflicts among residents."


The official added, "In April of this year, the eco-friendly integrated town project was selected as an exempt project from the preliminary feasibility study by the Ministry of Economy and Finance, and with 300 million won in national funding included in the 2026 government budget proposal, the project gained further momentum. Once the Korea Development Institute (KDI) completes its ongoing review of the project plan's adequacy, we will swiftly proceed with subsequent administrative procedures, including local finance investment reviews, aiming for completion in 2030."


However, local residents continue to express strong opposition. They have repeatedly held protest rallies to voice their stance, and even elderly residents over the age of 80 have joined the rallies, denouncing the unfairness of the site selection process and firmly opposing the installation.



Park Anam, co-chair of the Sejong City Northern Region Committee Against the Incineration Plant, said, "We were confident of victory and proceeded with the lawsuit because it was an unjust administrative procedure to collect signatures from people living in local nursing homes without resident consent. The committee feels disappointment and anger at the court's decision," adding, "We will gather residents' opinions and announce our response in due course."