Heavy Water Leak Occurs Inside Wolseong Unit 2 During Scheduled Preventive Maintenance
Wolseong Nuclear Power Headquarters of Korea Hydro & Nuclear Power (Director: Jung Wonho) announced that at approximately 4:30 a.m. on the 19th, during scheduled preventive maintenance, a portion of heavy water leaked inside the plant facilities while preparing to replace the moderator purification system filter in the auxiliary building of Wolseong Unit 2 (a 700,000 kW-class pressurized heavy water reactor).
Wolseong Nuclear Power Headquarters immediately shut down the relevant pump upon confirming the leak, thereby stopping further leakage. All of the leaked heavy water was collected in the reactor auxiliary building filter room and the internal sump, with no leakage to the outside. The amount of leakage identified so far is approximately 265 kg, and the exact amount is currently being verified.
Hot Picks Today
"Two Spend 500,000 Won in a Flash, Yet Wait Two Hours?" ... 'Dreamland' Shunned by Kids and Foreign Tourists
- The Era of Getting 200 Million Won After 30 Years Is Over... A Japanese Bank's "Perpetual Department Head" Who Just Clocked In Cries Out
- Spain Hit by Its Worst Tragedy... Lee Kangin, Moreno and Real Madrid Join Soccer World in Mourning
- They Said, “Make It Your Home for Life” - Then Suddenly Kicked 200 Passengers Off... What Happened to the Around-the-World Cruise?
- "130 Rice Bowls Sold Out in a Day"... 'Unfiltered Face' Adds 8 Million Won to Night Market Sales: China's Bungeunwoo
Wolseong Unit 2 has been undergoing scheduled preventive maintenance since September 1, and there is no external radiological impact. Wolseong Nuclear Power Headquarters plans to investigate the detailed cause and take appropriate measures.